Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
204
matching recommendationsNAICS | 33634 | Motor Vehicle Brake System Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0933 # 05 Y:2015 | 05 | 2015 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $4,075 | $0 | Implemented |
UD0933 # 06 Y:2015 | 06 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,155 | $2,950 | Not Implemented |
UD0933 # 07 Y:2015 | 07 | 2015 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $15,649 | $200 | Not Implemented |
UD0933 # 08 Y:2015 | 08 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,264 | $10,000 | Not Implemented |
UD0933 # 09 Y:2015 | 09 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $52,874 | $48,825 | Not Implemented |
UD0933 # 10 Y:2015 | 10 | 2015 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,237 | $0 | Not Implemented |
UD0933 # 11 Y:2015 | 11 | 2015 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $4,138 | $9,000 | Not Implemented |
UD0933 # 12 Y:2015 | 12 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $168,234 | $1,058,200 | Not Implemented |
UD0933 # 13 Y:2015 | 13 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,454 | $1,000 | Implemented |
UD0933 # 14 Y:2015 | 14 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,427 | $4,500 | Implemented |
UD0933 # 15 Y:2015 | 15 | 2015 | OPTIMIZE PLANT POWER FACTOR | $4,834 | $35,000 | Implemented |
OK0885 # 01 Y:2014 | 01 | 2014 | INSTALL OCCUPANCY SENSORS | $10,088 | $12,319 | Implemented |
OK0885 # 02 Y:2014 | 02 | 2014 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $42,502 | $2,889 | Implemented |
OK0885 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,111 | $1,900 | Implemented |
UM0439 # 01 Y:2014 | 01 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $32,824 | $20,000 | Not Implemented |
UM0439 # 02 Y:2014 | 02 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,150 | $21,000 | Not Implemented |
UM0439 # 03 Y:2014 | 03 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,596 | $2,500 | Implemented |
UM0439 # 04 Y:2014 | 04 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $27,566 | $4,000 | Implemented |
IA0505 # 01 Y:2013 | 01 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,932 | $1,010 | Not Implemented |
IA0505 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $503 | $50 | Implemented |
IA0505 # 03 Y:2013 | 03 | 2013 | INSULATE BARE EQUIPMENT | $319 | $100 | Implemented |
IA0505 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,467 | $845 | Implemented |
IA0505 # 05 Y:2013 | 05 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $795 | $200 | Implemented |
IA0505 # 06 Y:2013 | 06 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,315 | $910 | Implemented |
IA0505 # 07 Y:2013 | 07 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $920 | $233 | Implemented |