matching recommendationsNAICS | 33635 | Motor Vehicle Transmission and Power Train Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0236 # 03 Y:2020 | 03 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,481 | $0 | Implemented |
IC0236 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,626 | $4,075 | Implemented |
IC0236 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,924 | $30,183 | Implemented |
IP0092 # 01 Y:2017 | 01 | 2017 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,211 | $0 | Implemented |
IP0092 # 07 Y:2017 | 07 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $112,756 | $41,810 | Implemented |
IP0092 # 06 Y:2017 | 06 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,898 | $1,119 | Implemented |
IP0092 # 05 Y:2017 | 05 | 2017 | INSTALL OCCUPANCY SENSORS | $635 | $42 | Implemented |
IP0092 # 04 Y:2017 | 04 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $546 | $31 | Implemented |
IP0092 # 03 Y:2017 | 03 | 2017 | PAY BILLS ON TIME TO AVOID LATE FEES | $7,288 | $0 | Implemented |
IP0092 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $876 | $0 | Implemented |
UD0977 # 08 Y:2017 | 08 | 2017 | ADD AREA LIGHTING SWITCHES | $745 | $0 | Implemented |
UD0977 # 01 Y:2017 | 01 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $12,684 | $6,500 | Implemented |
UD0977 # 02 Y:2017 | 02 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,960 | $0 | Implemented |
UD0977 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,231 | $0 | Implemented |
UD0977 # 06 Y:2017 | 06 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $16,048 | $2,000 | Implemented |
IP0061 # 06 Y:2016 | 06 | 2016 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,664 | $3,260 | Implemented |
IP0061 # 08 Y:2016 | 08 | 2016 | RECYCLE WHITE WATER | $61,804 | $36,000 | Implemented |
IP0061 # 10 Y:2016 | 10 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,505 | $75,569 | Implemented |
IP0061 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $5,310 | $1,611 | Implemented |
IP0061 # 04 Y:2016 | 04 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $931 | $20 | Implemented |
IP0061 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,196 | $35 | Implemented |
IP0061 # 02 Y:2016 | 02 | 2016 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $2,745 | $0 | Implemented |
IP0061 # 01 Y:2016 | 01 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,775 | $4 | Implemented |
IP0034 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,112 | $0 | Implemented |