Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
230
matching recommendationsNAICS | 3391 | Medical Equipment and Supplies Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0259 # 03 Y:2014 | 03 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,650 | $3,100 | Implemented |
MI0259 # 04 Y:2014 | 04 | 2014 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,728 | $760 | Implemented |
MI0259 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,251 | $9,720 | Not Implemented |
MI0259 # 06 Y:2014 | 06 | 2014 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $3,604 | $8,400 | Not Implemented |
MI0259 # 07 Y:2014 | 07 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,090 | $1,040 | Implemented |
MI0259 # 08 Y:2014 | 08 | 2014 | INSTALL OCCUPANCY SENSORS | $1,545 | $622 | Implemented |
MI0259 # 09 Y:2014 | 09 | 2014 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $820 | $80 | Not Implemented |
MI0259 # 10 Y:2014 | 10 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $629 | $1,660 | Implemented |
MI0259 # 11 Y:2014 | 11 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $183 | $80 | Implemented |
MI0241 # 01 Y:2013 | 01 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $16,509 | $3,900 | Implemented |
MI0241 # 02 Y:2013 | 02 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,217 | $6,000 | Implemented |
MI0241 # 03 Y:2013 | 03 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $9,040 | $80 | Implemented |
MI0241 # 04 Y:2013 | 04 | 2013 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $7,960 | $540 | Implemented |
MI0241 # 05 Y:2013 | 05 | 2013 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,883 | $4,691 | Implemented |
MI0241 # 06 Y:2013 | 06 | 2013 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $2,564 | $440 | Implemented |
MI0241 # 07 Y:2013 | 07 | 2013 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $2,118 | $5,397 | Not Implemented |
MI0241 # 08 Y:2013 | 08 | 2013 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,942 | $2,196 | Implemented |
MI0241 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,593 | $1,660 | Implemented |
MI0241 # 10 Y:2013 | 10 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $955 | $80 | Not Implemented |
MI0241 # 11 Y:2013 | 11 | 2013 | INSULATE BARE EQUIPMENT | $686 | $1,520 | Implemented |
MI0241 # 12 Y:2013 | 12 | 2013 | INSTALL OCCUPANCY SENSORS | $542 | $209 | Not Implemented |
MI0208 # 01 Y:2011 | 01 | 2011 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $40,370 | $292,600 | Implemented |
MI0208 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,143 | $16,918 | Implemented |
MI0208 # 03 Y:2011 | 03 | 2011 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $25,727 | $48,170 | Implemented |
MI0208 # 04 Y:2011 | 04 | 2011 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $16,075 | $2,550 | Not Implemented |