Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsNAICS | 339112 | Surgical and Medical Instrument Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0812 # 05 Y:2020 | 05 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,774 | $16,650 | Implemented |
MA0812 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,190 | $5,960 | Implemented |
MA0812 # 03 Y:2020 | 03 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,615 | $32,940 | Implemented |
MA0804 # 05 Y:2019 | 05 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,134 | $1,000 | Implemented |
MA0804 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,014 | $300 | Implemented |
MA0804 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $100,108 | $144,760 | Implemented |
MA0789 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,415 | $29,288 | Implemented |
MA0662 # 07 Y:2010 | 07 | 2010 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $680 | $2,000 | Implemented |
MA0662 # 09 Y:2010 | 09 | 2010 | INSTALL OCCUPANCY SENSORS | $547 | $1,740 | Implemented |
MA0662 # 08 Y:2010 | 08 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $644 | $640 | Implemented |
MA0662 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $883 | $1,500 | Implemented |
MA0662 # 05 Y:2010 | 05 | 2010 | INSULATE BARE EQUIPMENT | $1,011 | $1,760 | Implemented |
MA0662 # 02 Y:2010 | 02 | 2010 | REDUCE VENTILATION AIR | $2,158 | $3,935 | Implemented |
MA0662 # 01 Y:2010 | 01 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,395 | $2,265 | Implemented |
MA0589 # 03 Y:2006 | 03 | 2006 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,300 | $4,000 | Implemented |
MA0589 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $177 | $800 | Implemented |
MA0589 # 08 Y:2006 | 08 | 2006 | INSULATE BARE EQUIPMENT | $187 | $60 | Implemented |
MA0589 # 07 Y:2006 | 07 | 2006 | INSULATE BARE EQUIPMENT | $2,060 | $1,800 | Implemented |
MA0589 # 06 Y:2006 | 06 | 2006 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,951 | $400 | Implemented |
MA0589 # 05 Y:2006 | 05 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,311 | $3,565 | Implemented |