Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsNAICS | 33992 | Sporting and Athletic Goods Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0205 # 07 Y:2022 | 07 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $382 | $720 | Not Implemented |
UU0205 # 06 Y:2022 | 06 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,070 | $150 | Not Implemented |
UU0205 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,293 | $198 | Implemented |
UU0205 # 04 Y:2022 | 04 | 2022 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $3,404 | $9,200 | Not Implemented |
UU0205 # 03 Y:2022 | 03 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,310 | $28,263 | Not Implemented |
UU0205 # 02 Y:2022 | 02 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $10,548 | $18,900 | Not Implemented |
UU0205 # 01 Y:2022 | 01 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,629 | $10,629 | Not Implemented |
AM0648 # 02 Y:2013 | 02 | 2013 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $29,607 | $0 | Implemented |
AM0648 # 11 Y:2013 | 11 | 2013 | INSULATE BARE EQUIPMENT | $101 | $308 | Not Implemented |
AM0648 # 10 Y:2013 | 10 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,116 | $9 | Implemented |
AM0648 # 09 Y:2013 | 09 | 2013 | USE SYNTHETIC LUBRICANT | $2,016 | $0 | Implemented |
AM0648 # 08 Y:2013 | 08 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,230 | $500 | Implemented |
AM0648 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,544 | $18,524 | Implemented |
AM0648 # 06 Y:2013 | 06 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,059 | $167 | Implemented |
AM0648 # 05 Y:2013 | 05 | 2013 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $10,304 | $45,000 | Implemented |
AM0648 # 04 Y:2013 | 04 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $10,740 | $0 | Implemented |
AM0648 # 03 Y:2013 | 03 | 2013 | OPTIMIZE PLANT POWER FACTOR | $16,856 | $22,350 | Implemented |
AM0648 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $52,176 | $5,000 | Implemented |
UU0065 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $4,060 | $5,520 | Not Implemented |
UU0065 # 02 Y:2004 | 02 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,450 | $0 | Implemented |
UU0065 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,345 | $1,100 | Implemented |
UU0065 # 04 Y:2004 | 04 | 2004 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,188 | $225 | Implemented |
UU0065 # 05 Y:2004 | 05 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,650 | $675 | Not Implemented |