Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
59
matching recommendationsNAICS | 511 | Publishing Industries (except Internet) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0294 # 08 Y:2004 | 08 | 2004 | USE PHOTOCELL CONTROLS | $803 | $1,378 | Not Implemented |
SF0294 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,895 | $3,045 | Not Implemented |
SF0294 # 06 Y:2004 | 06 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,595 | $32,955 | Not Implemented |
SF0294 # 05 Y:2004 | 05 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,833 | $2,526 | Not Implemented |
SF0294 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,414 | $22,970 | Implemented |
SF0294 # 03 Y:2004 | 03 | 2004 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,702 | $0 | Not Implemented |
SF0294 # 02 Y:2004 | 02 | 2004 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,624 | $0 | Not Implemented |
SF0294 # 11 Y:2004 | 11 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $31,801 | $29,800 | Not Implemented |
SF0294 # 10 Y:2004 | 10 | 2004 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,054 | $0 | Not Implemented |
SF0294 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,133 | $0 | Implemented |
SF0294 # 09 Y:2004 | 09 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,917 | $4,620 | Not Implemented |
AS0387 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,736 | $60 | Not Implemented |
AS0387 # 07 Y:2004 | 07 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,704 | $60 | Implemented |
AS0387 # 06 Y:2004 | 06 | 2004 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,180 | $10,083 | n/a |
AS0387 # 05 Y:2004 | 05 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,451 | $2,911 | Implemented |
AS0387 # 04 Y:2004 | 04 | 2004 | INSTALL OCCUPANCY SENSORS | $309 | $675 | Not Implemented |
AS0387 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,601 | $14,813 | n/a |
AS0387 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,518 | $500 | Not Implemented |
SU0190 # 08 Y:2004 | 08 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,600 | $19,500 | Not Implemented |
SU0190 # 01 Y:2004 | 01 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,548 | $0 | Implemented |
SU0190 # 05 Y:2004 | 05 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $97 | $108 | Implemented |
SU0190 # 02 Y:2004 | 02 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,782 | $0 | Implemented |
SU0190 # 07 Y:2004 | 07 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,329 | $3,430 | Not Implemented |
SU0190 # 03 Y:2004 | 03 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $205 | $0 | Implemented |
SU0190 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $891 | $180 | Implemented |