Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsNAICS | 712110 | Museums |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0454 # 07 Y:2012 | 07 | 2012 | IMPROVE SPACE COMFORT CONDITIONING | $41,033 | $60,000 | Not Implemented |
NC0454 # 06 Y:2012 | 06 | 2012 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,318 | $15,000 | Not Implemented |
NC0454 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $134 | $529 | Not Implemented |
NC0454 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $454 | $225 | Implemented |
NC0454 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,836 | $175 | Implemented |
NC0454 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,774 | $900 | Implemented |
NC0454 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,289 | $5,115 | Implemented |
NC0453 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $650 | $1,080 | Not Implemented |
NC0453 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,747 | $16,220 | Not Implemented |
NC0453 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,228 | $16,470 | Not Implemented |
NC0453 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $240 | $352 | Not Implemented |
NC0452 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,629 | $10,000 | Implemented |
NC0453 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,330 | $600 | Not Implemented |
NC0453 # 05 Y:2012 | 05 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,077 | $0 | Not Implemented |
NC0453 # 04 Y:2012 | 04 | 2012 | USE DEIONIZED WATER IN UPSTREAM RINSE TANKS | $4,110 | $5,000 | Not Implemented |
NC0453 # 03 Y:2012 | 03 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $598 | $1,000 | Not Implemented |
NC0453 # 02 Y:2012 | 02 | 2012 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,450 | $3,000 | Not Implemented |
NC0453 # 01 Y:2012 | 01 | 2012 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $36,712 | $21,000 | Not Implemented |
NC0452 # 05 Y:2012 | 05 | 2012 | USE SOLAR HEAT TO HEAT WATER | $10,485 | $62,000 | Not Implemented |
NC0452 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $270 | $297 | Not Implemented |
NC0452 # 03 Y:2012 | 03 | 2012 | INSTALL OCCUPANCY SENSORS | $269 | $375 | Not Implemented |
NC0452 # 02 Y:2012 | 02 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,864 | $3,200 | Implemented |