Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
94
matching recommendationsNAICS | 812 | Personal and Laundry Services |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS0224 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,796 | $25 | Implemented |
LS0224 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,962 | $75 | Implemented |
LS0224 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $38,021 | $514,800 | Not Implemented |
LS0224 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,495 | $20,000 | Not Implemented |
LS0224 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,104 | $1,413 | Implemented |
LS0224 # 05 Y:2024 | 05 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $175,678 | $600,000 | Implemented |
LS0224 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,486 | $113,400 | Not Implemented |
CI0026 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,454 | $2,400 | n/a |
CI0026 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,873 | $8,074 | n/a |
CI0026 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $500 | $2,000 | n/a |
CI0026 # 08 Y:2023 | 08 | 2023 | SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS | $458 | $400 | n/a |
CI0026 # 04 Y:2023 | 04 | 2023 | USE PHOTOCELL CONTROLS | $3,866 | $2,700 | n/a |
CI0026 # 01 Y:2023 | 01 | 2023 | REPLACE BOILER | $40,642 | $20,000 | n/a |
CI0026 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $6,141 | $80,118 | n/a |
CI0026 # 02 Y:2023 | 02 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $21,942 | $60,000 | n/a |
CI0013 # 10 Y:2023 | 10 | 2023 | SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS | $481 | $600 | n/a |
CI0013 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $27,121 | $0 | n/a |
CI0013 # 06 Y:2023 | 06 | 2023 | USE PHOTOCELL CONTROLS | $15,628 | $2,250 | n/a |
CI0013 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,946 | $2,400 | n/a |
CI0013 # 03 Y:2023 | 03 | 2023 | REPLACE BOILER | $37,870 | $9,000 | n/a |
CI0013 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,989 | $15,565 | n/a |
CI0013 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $1,704 | $2,000 | n/a |
CI0013 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,109 | $3,000 | n/a |
CI0013 # 07 Y:2023 | 07 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $13,319 | $60,000 | n/a |
CI0013 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $34,809 | $305,300 | n/a |