Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21,002
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2409 # 05 Y:2024 | 05 | 2024 | REPLACE BOILER | $61,679 | $155,400 | Implemented |
UW2409 # 06 Y:2024 | 06 | 2024 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $72,261 | $271,830 | Implemented |
UW2409 # 07 Y:2024 | 07 | 2024 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $24,670 | $223,625 | Implemented |
UL2406 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $21,720 | $14,950 | n/a |
UL2406 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $7,741 | $12,220 | n/a |
UL2406 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,721 | $15,563 | n/a |
UL2406 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $112 | $406 | n/a |
UL2406 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,826 | $10,980 | n/a |
UL2406 # 06 Y:2024 | 06 | 2024 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $4,470 | $1,120 | n/a |
UL2406 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,544 | $12,225 | n/a |
UL2406 # 08 Y:2024 | 08 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $78,236 | $775,946 | n/a |
UL2406 # 09 Y:2024 | 09 | 2024 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $35,350 | $159,350 | n/a |
LS2412 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,703 | $150 | Not Implemented |
LS2412 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $2,908 | $275 | Not Implemented |
LS2412 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $872 | $135 | Implemented |
LS2412 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,854 | $5,915 | Implemented |
LS2411 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,595 | $50 | Not Implemented |
LS2411 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $266 | $45 | Implemented |
LS2411 # 03 Y:2024 | 03 | 2024 | IMPROVE SPACE COMFORT CONDITIONING | $26,395 | $18,900 | Not Implemented |
LS2411 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,962 | $12,050 | Implemented |
LS2411 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $72,136 | $480,000 | Implemented |
SF0619 # 01 Y:2024 | 01 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $4,612 | $0 | n/a |
SF0619 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,589 | $220 | n/a |
SF0619 # 03 Y:2024 | 03 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $241 | $0 | n/a |
SF0619 # 04 Y:2024 | 04 | 2024 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $39,174 | $7,044 | n/a |