IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

587

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0070 # 06 Y:1993 06 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $407 $0 Not Implemented
IA0070 # 07 Y:1993 07 1993 INSTALL OCCUPANCY SENSORS $560 $1,539 Not Implemented
IA0069 # 01 Y:1993 01 1993 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST $363,236 $1,064,000 Not Implemented
IA0069 # 02 Y:1993 02 1993 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $62,688 $80,010 Not Implemented
IA0069 # 03 Y:1993 03 1993 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $13,911 $2,500 Implemented
IA0069 # 04 Y:1993 04 1993 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $2,716 $1,040 Implemented
IA0069 # 05 Y:1993 05 1993 RECOVER WASTE HEAT FROM EQUIPMENT $637 $1,700 Not Implemented
IA0069 # 06 Y:1993 06 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $720 $0 Implemented
IA0068 # 01 Y:1993 01 1993 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,350 $4,590 Implemented
IA0068 # 02 Y:1993 02 1993 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,707 $1,000 Implemented
IA0068 # 03 Y:1993 03 1993 DIRECT WARMEST AIR TO COMBUSTION INTAKE $1,173 $1,364 Not Implemented
IA0068 # 04 Y:1993 04 1993 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,627 $1,059 Not Implemented
IA0068 # 05 Y:1993 05 1993 INSTALL OCCUPANCY SENSORS $2,984 $3,213 Implemented
IA0068 # 06 Y:1993 06 1993 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,325 $2,625 Not Implemented
IA0068 # 07 Y:1993 07 1993 INSTALL / REPAIR INSULATION ON STEAM LINES $435 $168 Implemented
IA0062 # 01 Y:1993 01 1993 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $27,024 $4,200 Implemented
IA0062 # 02 Y:1993 02 1993 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $9,529 $250 Not Implemented
IA0062 # 03 Y:1993 03 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,185 $100 Implemented
IA0062 # 04 Y:1993 04 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,109 $1,500 Implemented
IA0062 # 05 Y:1993 05 1993 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $409 $175 Not Implemented
IA0062 # 06 Y:1993 06 1993 RECOVER WASTE HEAT FROM EQUIPMENT $229 $486 Implemented
IA0062 # 07 Y:1993 07 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,922 $1,083 Not Implemented
IA0062 # 08 Y:1993 08 1993 INSTALL OCCUPANCY SENSORS $1,689 $3,327 Not Implemented
IA0062 # 09 Y:1993 09 1993 OPTIMIZE PLANT POWER FACTOR $1,859 $6,615 Implemented
IA0060 # 01 Y:1993 01 1993 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $9,999 $4,200 Implemented