Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0540 # 06 Y:2023 | 06 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $11,386 | $45,000 | Not Implemented |
LE0540 # 07 Y:2023 | 07 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $128,214 | $580,000 | Not Implemented |
IP0166 # 01 Y:2022 | 01 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $12,766 | $0 | Not Implemented |
IP0166 # 02 Y:2022 | 02 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $4,102 | $0 | Not Implemented |
IP0166 # 03 Y:2022 | 03 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $9,132 | $0 | Not Implemented |
IP0166 # 04 Y:2022 | 04 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,623 | $0 | Implemented |
IP0166 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $526 | $33 | Implemented |
IP0166 # 06 Y:2022 | 06 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,625 | $3,274 | Implemented |
IP0166 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,433 | $1,162 | Implemented |
IP0166 # 08 Y:2022 | 08 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $704 | $1,279 | Not Implemented |
IP0166 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $198 | $416 | Implemented |
IP0166 # 10 Y:2022 | 10 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $279 | $665 | Implemented |
IP0166 # 11 Y:2022 | 11 | 2022 | OPTIMIZE PLANT POWER FACTOR | $11,046 | $43,200 | Implemented |
IP0166 # 12 Y:2022 | 12 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $136 | $665 | Implemented |
TT0291 # 01 Y:2023 | 01 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $44,264 | $3,287 | Not Implemented |
TT0291 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,378 | $10,100 | Implemented |
TT0291 # 03 Y:2023 | 03 | 2023 | PURCHASE APPROPRIATELY SIZED MATERIAL | $18,022 | $87,000 | Not Implemented |
TT0291 # 04 Y:2023 | 04 | 2023 | USE OPTIMUM THICKNESS INSULATION | $14,929 | $45,390 | Not Implemented |
TT0291 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,663 | $1,500 | Implemented |
TT0291 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $2,088 | $4,500 | Not Implemented |
SF0595 # 01 Y:2023 | 01 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,809 | $1,487 | Implemented |
SF0595 # 02 Y:2023 | 02 | 2023 | USE OPTIMUM THICKNESS INSULATION | $2,174 | $1,800 | Implemented |
SF0595 # 03 Y:2023 | 03 | 2023 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $9,134 | $7,644 | Not Implemented |
SF0595 # 04 Y:2023 | 04 | 2023 | HEAT WATER WITH EXHAUST HEAT | $37,173 | $32,818 | Not Implemented |
SF0595 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,989 | $21,654 | Implemented |