Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
445
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0596 # 05 Y:2012 | 05 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $15,326 | $6,711 | Not Implemented |
OR0596 # 06 Y:2012 | 06 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $80,359 | $51,328 | Not Implemented |
OR0596 # 07 Y:2012 | 07 | 2012 | TREAT AND REUSE RINSE WATERS | $48,291 | $10,000 | Implemented |
OR0587 # 01 Y:2012 | 01 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $11,403 | $11,403 | Not Implemented |
OR0587 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,687 | $1,000 | Not Implemented |
OR0587 # 03 Y:2012 | 03 | 2012 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $15,142 | $6,108 | Not Implemented |
OR0587 # 04 Y:2012 | 04 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,099 | $1,560 | Not Implemented |
OR0587 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $2,854 | $2,854 | Implemented |
OR0587 # 06 Y:2012 | 06 | 2012 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $7,810 | $9,114 | Not Implemented |
OR0587 # 07 Y:2012 | 07 | 2012 | Install Anaerobic Digester | $75,601 | $294,329 | Not Implemented |
OR0584 # 01 Y:2012 | 01 | 2012 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $6,320 | $0 | Not Implemented |
OR0584 # 02 Y:2012 | 02 | 2012 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,558 | $19,925 | Not Implemented |
OR0584 # 03 Y:2012 | 03 | 2012 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $16,839 | $29,000 | Not Implemented |
OR0584 # 04 Y:2012 | 04 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,631 | $27,000 | Not Implemented |
OR0584 # 05 Y:2012 | 05 | 2012 | MINIMIZE WATER USAGE | $4,574 | $7,000 | Not Implemented |
OR0584 # 06 Y:2012 | 06 | 2012 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $7,796 | $19,701 | Not Implemented |
OR0584 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54,152 | $251,677 | Not Implemented |
UW0050 # 01 Y:2011 | 01 | 2011 | PAY BILLS ON TIME TO AVOID LATE FEES | $0 | $0 | Implemented |
UW0049 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,931 | $67,308 | Not Implemented |
UW0049 # 02 Y:2011 | 02 | 2011 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $9,443 | $7,200 | Implemented |
UW0049 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,756 | $1,300 | Implemented |
UW0049 # 04 Y:2011 | 04 | 2011 | INSULATE BARE EQUIPMENT | $1,029 | $1,810 | Not Implemented |
UW0047 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,466 | $57,117 | Not Implemented |
UW0047 # 02 Y:2011 | 02 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,626 | $11,606 | Not Implemented |
UW0047 # 03 Y:2011 | 03 | 2011 | INSULATE BARE EQUIPMENT | $400 | $410 | Not Implemented |