Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0032 # 07 Y:2024 | 07 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,346 | $100 | n/a |
CI0032 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $1,100 | $2,025 | n/a |
CI0032 # 09 Y:2024 | 09 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $454 | $1,050 | n/a |
TT0310 # 01 Y:2024 | 01 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $25,939 | $3,600 | n/a |
TT0310 # 02 Y:2024 | 02 | 2024 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $10,414 | $17,000 | n/a |
TT0310 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,068 | $12,500 | n/a |
TT0310 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $7,227 | $9,500 | n/a |
TT0310 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $6,590 | $2,200 | n/a |
TT0310 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,799 | $60 | n/a |
TT0310 # 07 Y:2024 | 07 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $335 | $75 | n/a |
TR0056 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,264 | $1,159 | n/a |
TR0056 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT FOR HEAT | $45,845 | $271,563 | n/a |
TR0056 # 03 Y:2023 | 03 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $6,902 | $2,500 | n/a |
AM0913 # 01 Y:2024 | 01 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $206,260 | $1,610,000 | n/a |
AM0913 # 02 Y:2024 | 02 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $430,200 | $10,000 | n/a |
AM0913 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $48,970 | $2,000 | n/a |
AM0913 # 04 Y:2024 | 04 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $12,600 | $2,200 | n/a |
AM0913 # 05 Y:2024 | 05 | 2024 | OPTIMIZE PLANT POWER FACTOR | $10,340 | $19,040 | n/a |
AM0913 # 06 Y:2024 | 06 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,090 | $0 | n/a |
AM0913 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,000 | $15 | n/a |
AM0913 # 08 Y:2024 | 08 | 2024 | INSULATE BARE EQUIPMENT | $2,610 | $415 | n/a |
DL0239 # 01 Y:2024 | 01 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $17,306 | $1,250 | n/a |
DL0239 # 02 Y:2024 | 02 | 2024 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $6,623 | $17,500 | n/a |
DL0239 # 03 Y:2024 | 03 | 2024 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $37,050 | $110,000 | n/a |
DL0239 # 04 Y:2024 | 04 | 2024 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $61,029 | $10,000 | n/a |