Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
975
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0566 # 03 Y:2005 | 03 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,560 | $300 | Implemented |
CO0566 # 04 Y:2005 | 04 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,010 | $20,000 | Implemented |
CO0566 # 05 Y:2005 | 05 | 2005 | USE SOLAR HEAT TO HEAT MAKE-UP AIR | $5,080 | $38,680 | Not Implemented |
CO0566 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,170 | $6,180 | Not Implemented |
CO0566 # 07 Y:2005 | 07 | 2005 | INSTALL OCCUPANCY SENSORS | $1,000 | $640 | Not Implemented |
CO0565 # 01 Y:2005 | 01 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,830 | $26,240 | Not Implemented |
CO0565 # 02 Y:2005 | 02 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,150 | $1,210 | Implemented |
CO0565 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,930 | $8,780 | Not Implemented |
CO0565 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,830 | $270 | Implemented |
CO0565 # 05 Y:2005 | 05 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,160 | $4,070 | Not Implemented |
CO0565 # 06 Y:2005 | 06 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $490 | $500 | Implemented |
CO0565 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $200 | $500 | Not Implemented |
CO0565 # 08 Y:2005 | 08 | 2005 | INSTALL OCCUPANCY SENSORS | $130 | $210 | Not Implemented |
CO0563 # 01 Y:2005 | 01 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $56,710 | $346,448 | Implemented |
CO0563 # 02 Y:2005 | 02 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $26,550 | $89,981 | Implemented |
CO0563 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,440 | $9,180 | Not Implemented |
CO0563 # 04 Y:2005 | 04 | 2005 | USE SYNTHETIC LUBRICANT | $2,710 | $1,660 | Not Implemented |
CO0563 # 05 Y:2005 | 05 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $820 | $0 | Implemented |
CO0563 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,330 | $26,160 | Implemented |
CO0563 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,040 | $26,010 | Implemented |
CO0562 # 01 Y:2005 | 01 | 2005 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $15,350 | $10,080 | Not Implemented |
CO0562 # 02 Y:2005 | 02 | 2005 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $10,710 | $1,080 | Not Implemented |
CO0562 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,500 | $240 | Implemented |
CO0562 # 04 Y:2005 | 04 | 2005 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $150 | $120 | Implemented |
CO0562 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,290 | $13,190 | Not Implemented |