Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

533

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OD0150 # 04 Y:1999 04 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $611 $3,660 Not Implemented
OD0150 # 02 Y:1999 02 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $370 $400 Not Implemented
OD0150 # 05 Y:1999 05 1999 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $779 $0 Not Implemented
OD0150 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,354 $9,564 Not Implemented
OD0150 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $402 $20 Not Implemented
TN0650 # 09 Y:1999 09 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,555 $1,120 Not Implemented
TN0650 # 04 Y:1999 04 1999 INSULATE BARE EQUIPMENT $6,220 $2,180 Not Implemented
TN0650 # 01 Y:1999 01 1999 MODIFY CURRENT INCENTIVE PROGRAM $150,000 $30,000 Not Implemented
TN0650 # 07 Y:1999 07 1999 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $39,640 $30,500 Not Implemented
TN0650 # 02 Y:1999 02 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,400 $0 Implemented
TN0650 # 06 Y:1999 06 1999 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,960 $16,600 Not Implemented
TN0650 # 08 Y:1999 08 1999 USE MINIMUM STEAM OPERATING PRESSURE $5,280 $0 Not Implemented
TN0650 # 03 Y:1999 03 1999 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $8,150 $0 Implemented
TN0650 # 05 Y:1999 05 1999 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $6,350 $36,000 Not Implemented
AR0177 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,480 $1,214 Not Implemented
AR0177 # 02 Y:1999 02 1999 INSTALL / REPAIR INSULATION ON STEAM LINES $5,452 $6,656 Not Implemented
AR0177 # 03 Y:1999 03 1999 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $48,768 $92,500 Not Implemented
AR0177 # 04 Y:1999 04 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $5,480 $8,000 Not Implemented
AR0177 # 05 Y:1999 05 1999 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $384,000 $400,000 Not Implemented
UF0238 # 03 Y:1999 03 1999 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,287 $0 Implemented
UF0238 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,479 $7,893 Not Implemented
UF0238 # 04 Y:1999 04 1999 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF $584 $20 Implemented
UF0238 # 02 Y:1999 02 1999 USE OPTIMUM THICKNESS INSULATION $1,894 $1,361 Implemented
UF0238 # 06 Y:1999 06 1999 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,767 $1,605 Implemented
UF0238 # 05 Y:1999 05 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,670 $0 Implemented