Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsSIC | 201 | Meat Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0208 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $588 | $1,470 | Not Implemented |
OR0208 # 05 Y:1994 | 05 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,373 | $18,725 | Not Implemented |
OR0208 # 06 Y:1994 | 06 | 1994 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,482 | $0 | Not Implemented |
OR0130 # 02 Y:1991 | 02 | 1991 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $261 | $0 | Implemented |
OR0130 # 03 Y:1991 | 03 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $450 | $800 | Implemented |
OR0130 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,399 | $4,936 | Implemented |
OR0130 # 05 Y:1991 | 05 | 1991 | OPTIMIZE PLANT POWER FACTOR | $1,647 | $3,450 | Implemented |
OR0130 # 06 Y:1991 | 06 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $75 | $157 | Implemented |
OR0130 # 07 Y:1991 | 07 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,347 | $3,453 | Implemented |
OR0130 # 08 Y:1991 | 08 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $292 | $881 | Implemented |
OR0130 # 01 Y:1991 | 01 | 1991 | INSTALL SET-BACK TIMERS | $1,778 | $225 | Implemented |
OR0081 # 01 Y:1990 | 01 | 1990 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,762 | $68,000 | Implemented |
OR0081 # 02 Y:1990 | 02 | 1990 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $3,741 | $635 | Implemented |
OR0081 # 03 Y:1990 | 03 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,720 | $10,000 | Implemented |
OR0081 # 04 Y:1990 | 04 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,690 | $1,924 | Not Implemented |
OR0081 # 05 Y:1990 | 05 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $137 | $324 | Implemented |
OR0076 # 01 Y:1990 | 01 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,574 | $1,000 | Implemented |
OR0076 # 02 Y:1990 | 02 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,005 | $652 | Not Implemented |
OR0076 # 03 Y:1990 | 03 | 1990 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $655 | $345 | Implemented |
OR0076 # 04 Y:1990 | 04 | 1990 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $658 | $390 | Not Implemented |
OR0076 # 05 Y:1990 | 05 | 1990 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $3,222 | $3,600 | Not Implemented |
OR0076 # 06 Y:1990 | 06 | 1990 | INSULATE BARE EQUIPMENT | $206 | $333 | Implemented |
OR0076 # 07 Y:1990 | 07 | 1990 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,585 | $6,190 | Implemented |
OR0076 # 08 Y:1990 | 08 | 1990 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $434 | $1,118 | Implemented |
OR0076 # 09 Y:1990 | 09 | 1990 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $486 | $1,553 | Not Implemented |