Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
105
matching recommendationsSIC | 201 | Meat Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0169 # 02 Y:1989 | 02 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $582 | $740 | Implemented |
MA0169 # 01 Y:1989 | 01 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,187 | $1,752 | Not Implemented |
MA0169 # 04 Y:1989 | 04 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $231 | $0 | Implemented |
MA0169 # 03 Y:1989 | 03 | 1989 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $1,087 | $0 | Implemented |
MA0169 # 05 Y:1989 | 05 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $405 | $0 | Not Implemented |
GT0392 # 05 Y:1989 | 05 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,680 | $2,110 | Implemented |
GT0392 # 12 Y:1989 | 12 | 1989 | REDUCE OR ELIMINATE WASTE | $24,430 | $0 | Implemented |
GT0392 # 11 Y:1989 | 11 | 1989 | USE OPTIMUM THICKNESS INSULATION | $740 | $1,190 | Not Implemented |
GT0392 # 09 Y:1989 | 09 | 1989 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $41,430 | $16,000 | Implemented |
GT0392 # 08 Y:1989 | 08 | 1989 | USE OPTIMUM THICKNESS INSULATION | $14,830 | $22,000 | Not Implemented |
GT0390 # 03 Y:1989 | 03 | 1989 | INSULATE BARE EQUIPMENT | $534 | $1,020 | Implemented |
GT0390 # 05 Y:1989 | 05 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $219 | $350 | Implemented |
GT0392 # 03 Y:1989 | 03 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,625 | $0 | Implemented |
GT0392 # 07 Y:1989 | 07 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,120 | $1,220 | Implemented |
GT0392 # 02 Y:1989 | 02 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,803 | $2,217 | Implemented |
GT0392 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,550 | $0 | Implemented |
GT0390 # 08 Y:1989 | 08 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $14,700 | $0 | Implemented |
GT0390 # 07 Y:1989 | 07 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $68,230 | $29,500 | Implemented |
GT0390 # 06 Y:1989 | 06 | 1989 | USE COLD WASTE WATER TO COOL CHILLER FEED WATER | $14,480 | $16,950 | Not Implemented |
GT0390 # 04 Y:1989 | 04 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $423 | $210 | Implemented |
GT0392 # 04 Y:1989 | 04 | 1989 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $650 | $0 | Not Implemented |
GT0392 # 06 Y:1989 | 06 | 1989 | REPAIR AND ELIMINATE STEAM LEAKS | $3,490 | $375 | Implemented |
GT0390 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,040 | $0 | Implemented |
GT0392 # 10 Y:1989 | 10 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,490 | $27,500 | Not Implemented |
GT0390 # 02 Y:1989 | 02 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $604 | $2,400 | Implemented |