matching recommendationsSIC | 201 | Meat Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0422 # 05 Y:2012 | 05 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $662 | $228 | Not Implemented |
SF0422 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,287 | $3,924 | Not Implemented |
SF0422 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,693 | $31,027 | Not Implemented |
SF0422 # 10 Y:2012 | 10 | 2012 | ADOPT IN-HOUSE MATERIAL GENERATION | $15,798 | $22,322 | Not Implemented |
SF0422 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $1,288 | $3,390 | Not Implemented |
SF0422 # 04 Y:2012 | 04 | 2012 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $47,040 | $16,100 | Not Implemented |
SF0422 # 03 Y:2012 | 03 | 2012 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $36,414 | $12,500 | Not Implemented |
SF0422 # 02 Y:2012 | 02 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $642 | $43 | Not Implemented |
SF0422 # 06 Y:2012 | 06 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,464 | $10,283 | Not Implemented |
SF0422 # 01 Y:2012 | 01 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,969 | $0 | Not Implemented |
SD0458 # 06 Y:2012 | 06 | 2012 | INSULATE BARE EQUIPMENT | $7,861 | $8,422 | Not Implemented |
SD0458 # 02 Y:2012 | 02 | 2012 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $46,732 | $123,300 | Not Implemented |
SD0458 # 01 Y:2012 | 01 | 2012 | REDESIGN PROCESS | $272,976 | $164,279 | Not Implemented |
SD0458 # 04 Y:2012 | 04 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $22,833 | $11,000 | Not Implemented |
SD0458 # 03 Y:2012 | 03 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,502 | $58,740 | Not Implemented |
SD0458 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,667 | $34,450 | Implemented |
SD0458 # 07 Y:2012 | 07 | 2012 | USE MINIMUM STEAM OPERATING PRESSURE | $1,107 | $200 | Not Implemented |
SD0457 # 03 Y:2012 | 03 | 2012 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $66,646 | $142,500 | Not Implemented |
SD0457 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $77,740 | $9,900 | Implemented |
SD0457 # 01 Y:2012 | 01 | 2012 | UPGRADE OBSOLETE EQUIPMENT | $111,057 | $145,000 | Not Implemented |
SD0457 # 09 Y:2012 | 09 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,169 | $10,385 | Not Implemented |
SD0457 # 12 Y:2012 | 12 | 2012 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,808 | $200 | Not Implemented |
SD0457 # 07 Y:2012 | 07 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,316 | $50,240 | Implemented |
SD0457 # 08 Y:2012 | 08 | 2012 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $11,926 | $35,500 | Not Implemented |
SD0457 # 13 Y:2012 | 13 | 2012 | USE MINIMUM STEAM OPERATING PRESSURE | $781 | $200 | Not Implemented |