Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,773
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0037 # 06 Y:1985 | 06 | 1985 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,718 | $960 | Implemented |
CO0037 # 07 Y:1985 | 07 | 1985 | INSULATE BARE EQUIPMENT | $2,299 | $1,000 | Implemented |
CO0037 # 08 Y:1985 | 08 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,507 | $812 | Not Implemented |
KU0165 # 01 Y:1985 | 01 | 1985 | INCREASE AMOUNT OF CONDENSATE RETURNED | $28,837 | $33,000 | Implemented |
KU0165 # 02 Y:1985 | 02 | 1985 | HEAT WATER WITH EXHAUST HEAT | $20,949 | $37,000 | Implemented |
KU0165 # 03 Y:1985 | 03 | 1985 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,822 | $9,000 | Not Implemented |
KU0165 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,248 | $4,815 | Implemented |
KU0165 # 05 Y:1985 | 05 | 1985 | IMPROVE LUBRICATION PRACTICES | $10,224 | $8,000 | Implemented |
KU0165 # 06 Y:1985 | 06 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,321 | $1,020 | Implemented |
KU0165 # 07 Y:1985 | 07 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,984 | $50 | Implemented |
KU0165 # 08 Y:1985 | 08 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $998 | $450 | Implemented |
KU0165 # 09 Y:1985 | 09 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $468 | $400 | Implemented |
KU0165 # 10 Y:1985 | 10 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $484 | $400 | Implemented |
OK0166 # 01 Y:1985 | 01 | 1985 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $3,054 | $850 | Not Implemented |
OK0166 # 02 Y:1985 | 02 | 1985 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $34,175 | $6,260 | Not Implemented |
OK0166 # 03 Y:1985 | 03 | 1985 | INSULATE BARE EQUIPMENT | $5,377 | $2,398 | Implemented |
OK0166 # 04 Y:1985 | 04 | 1985 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $1,074 | $403 | Not Implemented |
OK0166 # 05 Y:1985 | 05 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,782 | $30,000 | Not Implemented |
OK0166 # 06 Y:1985 | 06 | 1985 | INSULATE BARE EQUIPMENT | $950 | $624 | Implemented |
MA0022 # 01 Y:1985 | 01 | 1985 | HEAT WATER WITH EXHAUST HEAT | $2,163 | $1,875 | Not Implemented |
MA0022 # 02 Y:1985 | 02 | 1985 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $753 | $1,827 | Implemented |
MA0022 # 03 Y:1985 | 03 | 1985 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $160 | $154 | Implemented |
MA0022 # 04 Y:1985 | 04 | 1985 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $283 | $0 | Implemented |
MA0022 # 05 Y:1985 | 05 | 1985 | OPTIMIZE PLANT POWER FACTOR | $432 | $289 | Implemented |
MA0022 # 06 Y:1985 | 06 | 1985 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,060 | $1,190 | Not Implemented |