Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,773
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0836 # 06 Y:2011 | 06 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,960 | $1,140 | Not Implemented |
UD0836 # 07 Y:2011 | 07 | 2011 | USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS | $12,875 | $15,000 | Not Implemented |
UD0836 # 08 Y:2011 | 08 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,572 | $99,100 | Not Implemented |
UD0836 # 09 Y:2011 | 09 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $25,293 | $18,000 | Not Implemented |
UD0836 # 10 Y:2011 | 10 | 2011 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $6,389 | $10,000 | Not Implemented |
SF0394 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,204 | $73 | Implemented |
SF0394 # 02 Y:2011 | 02 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $439 | $235 | Implemented |
SF0394 # 03 Y:2011 | 03 | 2011 | OPTIMIZE PLANT POWER FACTOR | $2,952 | $3,821 | Implemented |
SF0394 # 04 Y:2011 | 04 | 2011 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,879 | $3,638 | Implemented |
SF0394 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $7,621 | $11,002 | Implemented |
SF0394 # 06 Y:2011 | 06 | 2011 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,794 | $20,780 | Implemented |
SF0394 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $241 | $700 | Implemented |
SF0394 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,002 | $12,392 | Not Implemented |
SF0393 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,408 | $720 | Implemented |
SF0393 # 02 Y:2011 | 02 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $99,396 | $33,822 | Implemented |
SF0393 # 03 Y:2011 | 03 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,385 | $4,330 | Implemented |
SF0393 # 04 Y:2011 | 04 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,791 | $1,329 | Not Implemented |
SF0393 # 05 Y:2011 | 05 | 2011 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $153,800 | $220,659 | Not Implemented |
SF0393 # 06 Y:2011 | 06 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,218 | $19,157 | Not Implemented |
SF0393 # 07 Y:2011 | 07 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $32,171 | $34,310 | Implemented |
SF0393 # 08 Y:2011 | 08 | 2011 | INSULATE BARE EQUIPMENT | $6,132 | $17,178 | Implemented |
SF0393 # 09 Y:2011 | 09 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,350 | $25,921 | Implemented |
SF0393 # 10 Y:2011 | 10 | 2011 | INSTALL OCCUPANCY SENSORS | $3,016 | $14,478 | Implemented |
LE0309 # 01 Y:2010 | 01 | 2010 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $189,768 | $90,000 | Not Implemented |
LE0309 # 02 Y:2010 | 02 | 2010 | INSULATE BARE EQUIPMENT | $23,403 | $5,772 | Implemented |