Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
212
matching recommendationsSIC | 2022 | Cheese, Natural And Processed |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1405 # 07 Y:2014 | 07 | 2014 | OPTIMIZE PLANT POWER FACTOR | $20,457 | $15,610 | Implemented |
UK1405 # 08 Y:2014 | 08 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,745 | $46,464 | Implemented |
UK1405 # 09 Y:2014 | 09 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,146 | $1,540 | Implemented |
UK1405 # 10 Y:2014 | 10 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,374 | $24,100 | Implemented |
UK1405 # 14 Y:2014 | 14 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $103 | $30 | Implemented |
UK1405 # 12 Y:2014 | 12 | 2014 | INSULATE FEEDWATER TANK | $3,480 | $1,769 | Implemented |
BS0037 # 07 Y:2014 | 07 | 2014 | ISOLATE HOT OR COLD EQUIPMENT | $26 | $21 | Implemented |
BS0037 # 06 Y:2014 | 06 | 2014 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $674 | $575 | Implemented |
BS0037 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $330 | $1,042 | Implemented |
BS0037 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $517 | $2,038 | Implemented |
BS0037 # 01 Y:2014 | 01 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $108 | $540 | Implemented |
SF0419 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $637 | $80 | Implemented |
SF0419 # 04 Y:2012 | 04 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,431 | $16,162 | Implemented |
SF0407 # 02 Y:2012 | 02 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $7,965 | $672 | Implemented |
SF0407 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,152 | $672 | Implemented |
SF0407 # 06 Y:2012 | 06 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,437 | $1,299 | Implemented |
SF0404 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $697 | $1,356 | Implemented |
SF0404 # 10 Y:2011 | 10 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $676 | $1,569 | Implemented |
SF0404 # 04 Y:2011 | 04 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,934 | $5,426 | Implemented |
SF0404 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,243 | $0 | Implemented |
SF0404 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $257 | $22 | Implemented |
BD0393 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $201 | $10 | Implemented |
BD0393 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,288 | $107,000 | Implemented |
BD0393 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $155 | $300 | Implemented |
SD0434 # 01 Y:2011 | 01 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $799 | $100 | Implemented |