IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

39

matching recommendations
Reset
SIC 2026 Fluid Milk
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0506 # 04 Y:2021 04 2021 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $108,239 $800,000 Not Implemented
LE0506 # 03 Y:2021 03 2021 PREHEAT COMBUSTION AIR WITH WASTE HEAT $36,412 $80,000 Not Implemented
LE0506 # 02 Y:2021 02 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,519 $5,000 Not Implemented
LE0506 # 01 Y:2021 01 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $25,556 $11,500 Not Implemented
LE0309 # 09 Y:2010 09 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $24,018 $2,431 Implemented
LE0309 # 08 Y:2010 08 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,494 $40 Implemented
LE0309 # 07 Y:2010 07 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,657 $1,000 Implemented
LE0309 # 06 Y:2010 06 2010 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $6,925 $0 Implemented
LE0309 # 05 Y:2010 05 2010 PREHEAT COMBUSTION AIR WITH WASTE HEAT $11,117 $30,000 Not Implemented
LE0309 # 01 Y:2010 01 2010 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $189,768 $90,000 Not Implemented
LE0309 # 02 Y:2010 02 2010 INSULATE BARE EQUIPMENT $23,403 $5,772 Implemented
LE0309 # 03 Y:2010 03 2010 INSTALL TIMERS AND/OR THERMOSTATS $21,770 $250 Implemented
LE0309 # 04 Y:2010 04 2010 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $16,145 $20,000 Not Implemented
LE0245 # 02 Y:2006 02 2006 REPAIR OR REPLACE STEAM TRAPS $47,703 $5,000 Not Implemented
LE0245 # 10 Y:2006 10 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,488 $1,000 Not Implemented
LE0245 # 09 Y:2006 09 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $5,796 $3,000 Implemented
LE0245 # 08 Y:2006 08 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,646 $2,500 Not Implemented
LE0245 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,030 $2,000 Not Implemented
LE0245 # 06 Y:2006 06 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $9,828 $8,700 Implemented
LE0245 # 05 Y:2006 05 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $10,138 $2,500 Implemented
LE0245 # 04 Y:2006 04 2006 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $41,698 $30,000 Not Implemented
LE0245 # 03 Y:2006 03 2006 REUSE RICH WHITE WATER IN OTHER APPLICATIONS $43,680 $5,000 Not Implemented
LE0245 # 01 Y:2006 01 2006 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $318,192 $1,250 Not Implemented
WV0305 # 01 Y:2004 01 2004 INSULATE BARE EQUIPMENT $6,997 $96 Not Implemented
WV0305 # 02 Y:2004 02 2004 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $6,442 $1,774 Implemented