Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsSIC | 2026 | Fluid Milk |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LT0033 # 04 Y:1985 | 04 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,254 | $510 | Implemented |
LT0033 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,004 | $1,862 | Implemented |
LT0033 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,092 | $400 | Implemented |
LT0033 # 01 Y:1985 | 01 | 1985 | OPTIMIZE PLANT POWER FACTOR | $10,900 | $12,000 | Implemented |
LT0033 # 09 Y:1985 | 09 | 1985 | INSULATE BARE EQUIPMENT | $673 | $438 | Implemented |
LT0033 # 08 Y:1985 | 08 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $872 | $300 | Implemented |
LT0033 # 07 Y:1985 | 07 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,592 | $2,250 | Implemented |
LT0033 # 06 Y:1985 | 06 | 1985 | INSULATE BARE EQUIPMENT | $302 | $226 | Implemented |
LT0033 # 05 Y:1985 | 05 | 1985 | INSULATE BARE EQUIPMENT | $142 | $225 | Implemented |
CO0037 # 01 Y:1985 | 01 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $229 | $50 | Not Implemented |
CO0037 # 08 Y:1985 | 08 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,507 | $812 | Not Implemented |
CO0037 # 07 Y:1985 | 07 | 1985 | INSULATE BARE EQUIPMENT | $2,299 | $1,000 | Implemented |
CO0037 # 06 Y:1985 | 06 | 1985 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,718 | $960 | Implemented |
CO0037 # 05 Y:1985 | 05 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $293 | $150 | Not Implemented |
CO0037 # 04 Y:1985 | 04 | 1985 | INSTALL TURBULATORS | $2,037 | $1,200 | Not Implemented |
CO0037 # 03 Y:1985 | 03 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,658 | $8,000 | Not Implemented |
CO0037 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,071 | $500 | Implemented |
OK0166 # 06 Y:1985 | 06 | 1985 | INSULATE BARE EQUIPMENT | $950 | $624 | Implemented |
OK0166 # 01 Y:1985 | 01 | 1985 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $3,054 | $850 | Not Implemented |
OK0166 # 02 Y:1985 | 02 | 1985 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $34,175 | $6,260 | Not Implemented |
OK0166 # 03 Y:1985 | 03 | 1985 | INSULATE BARE EQUIPMENT | $5,377 | $2,398 | Implemented |
OK0166 # 04 Y:1985 | 04 | 1985 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $1,074 | $403 | Not Implemented |
OK0166 # 05 Y:1985 | 05 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,782 | $30,000 | Not Implemented |
CO0016 # 11 Y:1985 | 11 | 1985 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $1,879 | $2,500 | Not Implemented |
CO0016 # 10 Y:1985 | 10 | 1985 | INSTALL TURBULATORS | $5,512 | $1,000 | Not Implemented |