Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsSIC | 2026 | Fluid Milk |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0115 # 04 Y:1998 | 04 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $12,000 | $700 | n/a |
OD0115 # 03 Y:1998 | 03 | 1998 | KEEP BOILER TUBES CLEAN | $140 | $150 | n/a |
OD0115 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $42 | $83 | n/a |
OD0115 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $479 | $765 | n/a |
DS0113 # 06 Y:1998 | 06 | 1998 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $344 | $0 | Not Implemented |
DS0113 # 05 Y:1998 | 05 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,147 | $280 | Not Implemented |
DS0113 # 04 Y:1998 | 04 | 1998 | MINIMIZE WATER USAGE | $322 | $448 | Not Implemented |
DS0113 # 03 Y:1998 | 03 | 1998 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $16,899 | $444 | Not Implemented |
DS0113 # 02 Y:1998 | 02 | 1998 | INSULATE BARE EQUIPMENT | $827 | $598 | Not Implemented |
DS0113 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,935 | $14,709 | Not Implemented |
AM0311 # 12 Y:1998 | 12 | 1998 | INSTALL OCCUPANCY SENSORS | $250 | $485 | Not Implemented |
AM0311 # 01 Y:1998 | 01 | 1998 | REMOVE SLUDGE FROM TANKS ON A REGULAR BASIS | $116,000 | $900,000 | Not Implemented |
AM0311 # 11 Y:1998 | 11 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $290 | $93 | Not Implemented |
AM0311 # 10 Y:1998 | 10 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,105 | $1,205 | Implemented |
AM0311 # 09 Y:1998 | 09 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,400 | $0 | Not Implemented |
AM0311 # 08 Y:1998 | 08 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,500 | $2,100 | Implemented |
AM0311 # 07 Y:1998 | 07 | 1998 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,620 | $1,010 | Implemented |
AM0311 # 06 Y:1998 | 06 | 1998 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $2,170 | $0 | Implemented |
AM0311 # 05 Y:1998 | 05 | 1998 | USE SYNTHETIC LUBRICANT | $2,785 | $0 | Not Implemented |
AM0311 # 04 Y:1998 | 04 | 1998 | USE PHOTOCELL CONTROLS | $11,300 | $340 | Implemented |
AM0311 # 03 Y:1998 | 03 | 1998 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $23,800 | $1,515 | Not Implemented |
AM0311 # 02 Y:1998 | 02 | 1998 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $31,316 | $0 | Implemented |