Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
102
matching recommendationsSIC | 203 | Preserved Fruits And Vegetables |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0148 # 08 Y:2002 | 08 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $70 | $60 | Implemented |
SU0148 # 01 Y:2002 | 01 | 2002 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $163,907 | $767,895 | Not Implemented |
SU0148 # 02 Y:2002 | 02 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $25,533 | $0 | Implemented |
SU0148 # 07 Y:2002 | 07 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $105 | $0 | Implemented |
SU0148 # 04 Y:2002 | 04 | 2002 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $31,584 | $17,490 | Implemented |
SU0148 # 05 Y:2002 | 05 | 2002 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $9,006 | $3,700 | Implemented |
SU0148 # 03 Y:2002 | 03 | 2002 | MODIFY WORKLOAD | $14,400 | $20,000 | Implemented |
SU0148 # 06 Y:2002 | 06 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,438 | $320 | Not Implemented |
OR0422 # 02 Y:2002 | 02 | 2002 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $4,106 | $2,000 | Implemented |
OR0422 # 03 Y:2002 | 03 | 2002 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $6,975 | $5,500 | Implemented |
OR0422 # 05 Y:2002 | 05 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $595 | $0 | Implemented |
OR0422 # 04 Y:2002 | 04 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,944 | $2,953 | Implemented |
OR0422 # 01 Y:2002 | 01 | 2002 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,067 | $0 | Implemented |
SF0244 # 05 Y:2002 | 05 | 2002 | INSTALL OCCUPANCY SENSORS | $2,185 | $1,200 | Not Implemented |
SF0244 # 02 Y:2002 | 02 | 2002 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $107,810 | $50,000 | Implemented |
SF0244 # 06 Y:2002 | 06 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,304 | $4,110 | Implemented |
SF0244 # 04 Y:2002 | 04 | 2002 | REDUCE FLUID FLOW RATES | $31,494 | $16,627 | Implemented |
SF0244 # 10 Y:2002 | 10 | 2002 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $319 | $393 | Not Implemented |
SF0244 # 09 Y:2002 | 09 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,672 | $2,500 | Not Implemented |
SF0244 # 07 Y:2002 | 07 | 2002 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $21,274 | $17,580 | Implemented |
SF0244 # 12 Y:2002 | 12 | 2002 | TREAT AND REUSE RINSE WATERS | $218,183 | $18,705 | n/a |
SF0244 # 11 Y:2002 | 11 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,487 | $14,055 | Not Implemented |
SF0244 # 14 Y:2002 | 14 | 2002 | OPTIMIZE PLANT POWER FACTOR | $2,389 | $3,651 | Not Implemented |
SF0244 # 16 Y:2002 | 16 | 2002 | INSTALL AUTOMATIC PACKING EQUIPMENT | $101,519 | $350,000 | Implemented |
SF0244 # 15 Y:2002 | 15 | 2002 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $72,375 | $160,000 | Not Implemented |