Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsSIC | 2032 | Canned Specialties |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0839 # 05 Y:2011 | 05 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,623 | $5,000 | Not Implemented |
UD0839 # 14 Y:2011 | 14 | 2011 | INSTALL FOSSIL FUEL MAKE-UP AIR UNIT | $3,732 | $25 | Not Implemented |
UD0839 # 13 Y:2011 | 13 | 2011 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $48,911 | $75,000 | Implemented |
UD0839 # 12 Y:2011 | 12 | 2011 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,987 | $993 | Implemented |
UD0839 # 11 Y:2011 | 11 | 2011 | REPAIR AND ELIMINATE STEAM LEAKS | $5,425 | $2,100 | Implemented |
UD0839 # 10 Y:2011 | 10 | 2011 | OPERATE BOILERS ON HIGH FIRE SETTING | $11,810 | $23,620 | Implemented |
UD0839 # 09 Y:2011 | 09 | 2011 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,418 | $3,000 | Implemented |
UD0839 # 08 Y:2011 | 08 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $80,401 | $90,000 | Not Implemented |
UD0839 # 07 Y:2011 | 07 | 2011 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $29,882 | $59,764 | Not Implemented |
UD0839 # 06 Y:2011 | 06 | 2011 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $80,401 | $90,000 | Not Implemented |
UD0839 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,472 | $0 | Implemented |
UD0839 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $58,395 | $500 | Implemented |
UD0839 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $1,620 | $1,875 | Not Implemented |
UD0839 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,985 | $5,668 | Implemented |
UD0519 # 01 Y:1997 | 01 | 1997 | USE GRAVITY FEEDS WHEREVER POSSIBLE | $9,099 | $5,828 | Implemented |
UD0519 # 05 Y:1997 | 05 | 1997 | INSTALL EQUIPMENT TO MOVE PRODUCT | $14,413 | $6,000 | Implemented |
UD0519 # 04 Y:1997 | 04 | 1997 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $811 | $0 | Implemented |
UD0519 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $453 | $888 | Implemented |
UD0519 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $557 | $1,915 | Implemented |