IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

62

matching recommendations
Reset
SIC 204 Grain Mill Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0279 # 07 Y:1989 07 1989 REPAIR AND ELIMINATE STEAM LEAKS $22,796 $0 Implemented
OK0279 # 09 Y:1989 09 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $697 $513 Implemented
OK0279 # 08 Y:1989 08 1989 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $18,520 $38,000 Not Implemented
OK0279 # 06 Y:1989 06 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $15,332 $1,500 Implemented
OK0279 # 04 Y:1989 04 1989 INSULATE BARE EQUIPMENT $5,203 $2,516 Not Implemented
OK0279 # 03 Y:1989 03 1989 INSULATE BARE EQUIPMENT $2,236 $2,512 Not Implemented
OK0279 # 02 Y:1989 02 1989 INSTALL SET-BACK TIMERS $506 $400 Implemented
KU0278 # 06 Y:1989 06 1989 IMPROVE LUBRICATION PRACTICES $802 $0 Not Implemented
KU0278 # 02 Y:1989 02 1989 INSULATE BARE EQUIPMENT $531 $500 Not Implemented
KU0278 # 04 Y:1989 04 1989 REPAIR AND ELIMINATE STEAM LEAKS $295 $400 Implemented
KU0278 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $472 $600 Implemented
KU0278 # 01 Y:1989 01 1989 INSULATE BARE EQUIPMENT $325 $600 Implemented
CO0144 # 07 Y:1989 07 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $678 $200 Implemented
CO0144 # 09 Y:1989 09 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $214 $267 Implemented
CO0144 # 08 Y:1989 08 1989 INSTALL TIMERS AND/OR THERMOSTATS $500 $450 Implemented
CO0144 # 06 Y:1989 06 1989 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,942 $3,500 Implemented
CO0144 # 05 Y:1989 05 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,949 $5,481 Not Implemented
CO0144 # 04 Y:1989 04 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $963 $0 Implemented
CO0144 # 03 Y:1989 03 1989 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $5,856 $1,500 Implemented
CO0144 # 02 Y:1989 02 1989 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $2,253 $13,500 Not Implemented
CO0144 # 01 Y:1989 01 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,650 $500 Implemented
AM0056 # 04 Y:1989 04 1989 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $849 $960 Not Implemented
AM0056 # 03 Y:1989 03 1989 INSTALL SET-BACK TIMERS $970 $0 Implemented
AM0056 # 02 Y:1989 02 1989 RECOVER WASTE HEAT FROM EQUIPMENT $1,070 $700 Implemented
AM0056 # 01 Y:1989 01 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,790 $7,577 Not Implemented