IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

54

matching recommendations
Reset
SIC 204 Grain Mill Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
KU0546 # 05 Y:2000 05 2000 RECOVER WASTE HEAT FROM EQUIPMENT $870 $740 Implemented
KU0543 # 03 Y:2000 03 2000 INSTALL OCCUPANCY SENSORS $430 $450 Not Implemented
KU0543 # 08 Y:2000 08 2000 $56,920 $70,000 Not Implemented
KU0543 # 07 Y:2000 07 2000 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $5,630 $8,000 Not Implemented
KU0543 # 06 Y:2000 06 2000 ELIMINATE A BY-PRODUCT $7,940 $9,680 Not Implemented
KU0543 # 05 Y:2000 05 2000 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $420 $100 Implemented
KU0543 # 04 Y:2000 04 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $430 $50 Implemented
KU0543 # 02 Y:2000 02 2000 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $25,020 $50,000 Not Implemented
KU0543 # 01 Y:2000 01 2000 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $27,200 $0 Implemented
NV0149 # 01 Y:2000 01 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $342 $100 Implemented
NV0149 # 02 Y:2000 02 2000 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $454 $0 Not Implemented
NV0149 # 03 Y:2000 03 2000 $37,440 $80,000 Not Implemented
NV0149 # 04 Y:2000 04 2000 $21,840 $0 Not Implemented
DS0162 # 07 Y:2000 07 2000 $420 $0 n/a
DS0162 # 06 Y:2000 06 2000 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $252 $0 n/a
DS0162 # 05 Y:2000 05 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $499 $105 n/a
DS0162 # 04 Y:2000 04 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,182 $1,702 n/a
DS0162 # 03 Y:2000 03 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,888 $6,600 n/a
DS0162 # 01 Y:2000 01 2000 USE OPTIMUM THICKNESS INSULATION $4,196 $3,997 n/a
DS0162 # 02 Y:2000 02 2000 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $762 $0 n/a
UF0248 # 07 Y:2000 07 2000 DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING $1,786 $909 Implemented
UF0248 # 01 Y:2000 01 2000 $15,000 $50 Not Implemented
UF0248 # 02 Y:2000 02 2000 OPTIMIZE PLANT POWER FACTOR $3,807 $5,000 Implemented
UF0248 # 04 Y:2000 04 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,859 $600 Implemented
UF0248 # 05 Y:2000 05 2000 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $3,292 $6,686 Implemented