Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
59
matching recommendationsSIC | 204 | Grain Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0035 # 02 Y:1988 | 02 | 1988 | INSTALL SET-BACK TIMERS | $603 | $0 | Implemented |
OK0269 # 03 Y:1988 | 03 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $690 | $1,414 | Not Implemented |
OK0269 # 02 Y:1988 | 02 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44 | $103 | Implemented |
OK0269 # 06 Y:1988 | 06 | 1988 | REPAIR OR REPLACE STEAM TRAPS | $1,259 | $300 | Implemented |
OK0269 # 04 Y:1988 | 04 | 1988 | IMPROVE LUBRICATION PRACTICES | $1,262 | $0 | Implemented |
OK0269 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $92 | $88 | Implemented |
OK0269 # 05 Y:1988 | 05 | 1988 | INSTALL TURBULATORS | $700 | $760 | Not Implemented |
OR0035 # 13 Y:1988 | 13 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $19,951 | $1,500 | Implemented |
OR0035 # 12 Y:1988 | 12 | 1988 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,996 | $17,765 | Not Implemented |
OR0035 # 11 Y:1988 | 11 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $204 | $345 | Implemented |
OR0035 # 10 Y:1988 | 10 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $219 | $172 | Implemented |
OR0035 # 09 Y:1988 | 09 | 1988 | RECOVER AND REUSE COOLING WATER | $99,151 | $100,000 | Implemented |
OR0035 # 08 Y:1988 | 08 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $277 | $248 | Implemented |
OR0035 # 07 Y:1988 | 07 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $761 | $521 | Implemented |
OR0035 # 06 Y:1988 | 06 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $176 | $67 | Implemented |
OR0035 # 05 Y:1988 | 05 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $944 | $236 | Implemented |
OR0035 # 04 Y:1988 | 04 | 1988 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $459 | $250 | Not Implemented |
OR0035 # 03 Y:1988 | 03 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,267 | $300 | Implemented |
OR0035 # 01 Y:1988 | 01 | 1988 | USE MINIMUM STEAM OPERATING PRESSURE | $2,098 | $0 | Not Implemented |
OK0266 # 05 Y:1988 | 05 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,764 | $7,051 | Implemented |
OK0266 # 02 Y:1988 | 02 | 1988 | OPTIMIZE PLANT POWER FACTOR | $1,083 | $1,075 | Implemented |
OK0266 # 01 Y:1988 | 01 | 1988 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $15,319 | $37,200 | Implemented |
OK0266 # 06 Y:1988 | 06 | 1988 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $224 | $312 | Not Implemented |
OK0266 # 04 Y:1988 | 04 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $693 | $945 | Implemented |
OK0266 # 03 Y:1988 | 03 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $162 | $329 | Implemented |