Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,400
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0239 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,050 | $1,400 | n/a |
UU0239 # 04 Y:2024 | 04 | 2024 | INSULATE BARE EQUIPMENT | $6,144 | $7,887 | n/a |
UU0239 # 01 Y:2024 | 01 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $21,184 | $8,000 | n/a |
UU0239 # 03 Y:2024 | 03 | 2024 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $9,905 | $9,905 | n/a |
UU0239 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,011 | $3,011 | n/a |
UU0239 # 02 Y:2024 | 02 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $18,178 | $2,000 | n/a |
SF0600 # 01 Y:2023 | 01 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $18,276 | $0 | Not Implemented |
SF0600 # 04 Y:2023 | 04 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $17,278 | $24,708 | Not Implemented |
SF0600 # 06 Y:2023 | 06 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $50,839 | $316,988 | Implemented |
SF0600 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $738 | $50 | Implemented |
SF0600 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,662 | $6,270 | Not Implemented |
SF0600 # 05 Y:2023 | 05 | 2023 | INSULATE BARE EQUIPMENT | $937 | $3,563 | Not Implemented |
IP0172 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,640 | $132 | Not Implemented |
IP0172 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,870 | $1,313 | Not Implemented |
IP0172 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,584 | $8,088 | Not Implemented |
IP0172 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,315 | $14,588 | Not Implemented |
IP0172 # 02 Y:2023 | 02 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $512 | $83 | Not Implemented |
MS0413 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,019 | $1,523 | n/a |
MS0413 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,194 | $17,530 | n/a |
MS0413 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $225 | $341 | n/a |
MS0413 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $35,830 | $456,750 | n/a |
MS0413 # 05 Y:2023 | 05 | 2023 | INSULATE BARE EQUIPMENT | $11,256 | $11,275 | n/a |
UW2303 # 06 Y:2023 | 06 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,084 | $5,025 | Not Implemented |
UW2303 # 05 Y:2023 | 05 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $199 | $282 | Not Implemented |
UW2303 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $702 | $959 | Not Implemented |