Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,448
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1111 # 05 Y:2025 | 05 | 2025 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,836 | $2,500 | n/a |
UD1111 # 01 Y:2025 | 01 | 2025 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $38,544 | $2,352 | n/a |
UD1111 # 04 Y:2025 | 04 | 2025 | INSTALL OCCUPANCY SENSORS | $621 | $782 | n/a |
UC2417 # 03 Y:2024 | 03 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,989 | $7,146 | n/a |
UC2417 # 06 Y:2024 | 06 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,329 | $0 | n/a |
UC2417 # 02 Y:2024 | 02 | 2024 | OPTIMIZE PLANT POWER FACTOR | $2,644 | $9,173 | n/a |
UC2417 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $5,554 | $1,050 | n/a |
UC2417 # 01 Y:2024 | 01 | 2024 | PAY UTILITY BILLS ON TIME | $888 | $0 | n/a |
UC2417 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,301 | $75 | n/a |
TT0310 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,068 | $12,500 | n/a |
TT0310 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $7,227 | $9,500 | n/a |
TT0310 # 07 Y:2024 | 07 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $335 | $75 | n/a |
TT0310 # 02 Y:2024 | 02 | 2024 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $10,414 | $17,000 | n/a |
TT0310 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,799 | $60 | n/a |
TT0310 # 01 Y:2024 | 01 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $25,939 | $3,600 | n/a |
TT0310 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $6,590 | $2,200 | n/a |
LE0562 # 03 Y:2024 | 03 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $27,865 | $27,000 | Not Implemented |
LE0562 # 05 Y:2024 | 05 | 2024 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $727 | $1,000 | Implemented |
LE0562 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $4,513 | $320 | Implemented |
LE0562 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,738 | $13,669 | Not Implemented |
LE0562 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $1,612 | $350 | Implemented |
LE0562 # 08 Y:2024 | 08 | 2024 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $13,989 | $60,600 | Not Implemented |
LE0562 # 07 Y:2024 | 07 | 2024 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $3,491 | $8,000 | Implemented |
LE0562 # 04 Y:2024 | 04 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $4,836 | $5,000 | Not Implemented |
IC0302 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $215 | $1,256 | Implemented |