Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0835 # 02 Y:2022 | 02 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,773 | $7,150 | Implemented |
MA0835 # 03 Y:2022 | 03 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $18,072 | $14,280 | Not Implemented |
MA0835 # 04 Y:2022 | 04 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $680 | $750 | Implemented |
MA0835 # 05 Y:2022 | 05 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,360 | $625 | Not Implemented |
MA0835 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,572 | $40,722 | Implemented |
MA0836 # 05 Y:2022 | 05 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,531 | $1,500 | Implemented |
MA0836 # 08 Y:2022 | 08 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,781 | $625 | Implemented |
MA0836 # 07 Y:2022 | 07 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,777 | $7,150 | Implemented |
MA0836 # 06 Y:2022 | 06 | 2022 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $7,372 | $500 | Implemented |
MA0836 # 04 Y:2022 | 04 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,264 | $875 | Not Implemented |
MA0836 # 03 Y:2022 | 03 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $9,895 | $23,950 | Implemented |
MA0836 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,598 | $34,642 | Not Implemented |
MA0836 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $16,115 | $39,510 | Not Implemented |
ME0185 # 05 Y:1996 | 05 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,854 | $1,050 | Implemented |
ME0185 # 09 Y:1996 | 09 | 1996 | CLOSE OFF UNNEEDED STEAM LINES | $812 | $1,850 | Implemented |
ME0185 # 08 Y:1996 | 08 | 1996 | INSULATE BARE EQUIPMENT | $660 | $1,000 | Implemented |
ME0185 # 07 Y:1996 | 07 | 1996 | INSULATE BARE EQUIPMENT | $655 | $1,000 | Implemented |
ME0185 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,255 | $1,200 | Implemented |
ME0185 # 04 Y:1996 | 04 | 1996 | OPTIMIZE PLANT POWER FACTOR | $4,144 | $5,290 | Implemented |
ME0185 # 06 Y:1996 | 06 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,128 | $70 | Implemented |
ME0185 # 01 Y:1996 | 01 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,254 | $2,600 | Implemented |
ME0185 # 02 Y:1996 | 02 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,498 | $5,100 | Implemented |
ME0141 # 01 Y:1994 | 01 | 1994 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $4,492 | $14,000 | Not Implemented |
ME0141 # 03 Y:1994 | 03 | 1994 | IMPROVE COMBUSTION CONTROL CAPABILITY | $1,896 | $660 | Not Implemented |
ME0141 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,292 | $0 | Implemented |