Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
77
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0239 # 17 Y:2003 | 17 | 2003 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $2,000 | $500 | Not Implemented |
BD0239 # 10 Y:2003 | 10 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,591 | $0 | Not Implemented |
BD0239 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,133 | $4,850 | Implemented |
BD0239 # 08 Y:2003 | 08 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,532 | $2,000 | Implemented |
BD0239 # 07 Y:2003 | 07 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,876 | $4,580 | Implemented |
BD0239 # 06 Y:2003 | 06 | 2003 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $3,041 | $2,000 | Not Implemented |
BD0239 # 05 Y:2003 | 05 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $5,974 | $2,300 | Implemented |
BD0239 # 04 Y:2003 | 04 | 2003 | INSTALL SKYLIGHTS | $6,436 | $3,500 | Not Implemented |
BD0239 # 03 Y:2003 | 03 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,587 | $1,000 | Implemented |
BD0239 # 02 Y:2003 | 02 | 2003 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $14,284 | $500 | Implemented |
BD0239 # 01 Y:2003 | 01 | 2003 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $209,343 | $52,500 | Not Implemented |
BD0239 # 11 Y:2003 | 11 | 2003 | INSTALL OCCUPANCY SENSORS | $1,457 | $675 | Implemented |
BD0239 # 12 Y:2003 | 12 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $704 | $1,290 | Implemented |
BD0239 # 13 Y:2003 | 13 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $311 | $318 | Implemented |
BD0239 # 15 Y:2003 | 15 | 2003 | CHANGE OPERATING CONDITIONS | $63,779 | $10,000 | Implemented |
BD0239 # 16 Y:2003 | 16 | 2003 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,048 | $0 | Not Implemented |
BD0239 # 14 Y:2003 | 14 | 2003 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,140 | $1,000 | Implemented |
AS0362 # 01 Y:2003 | 01 | 2003 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $577 | $0 | Implemented |
AS0362 # 05 Y:2003 | 05 | 2003 | INSTALL EQUIPMENT TO MOVE PRODUCT | $16,801 | $2,470 | Implemented |
AS0362 # 04 Y:2003 | 04 | 2003 | INSTALL EQUIPMENT TO MOVE PRODUCT | $6,720 | $4,060 | Implemented |
AS0362 # 03 Y:2003 | 03 | 2003 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $922 | $4,350 | Implemented |
AS0362 # 02 Y:2003 | 02 | 2003 | INSTALL OCCUPANCY SENSORS | $141 | $450 | Not Implemented |
SD0328 # 03 Y:2003 | 03 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,323 | $0 | Implemented |
SD0328 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $269,910 | $1,371,000 | Implemented |
SD0328 # 02 Y:2003 | 02 | 2003 | INSTALL SKYLIGHTS | $5,260 | $6,650 | Not Implemented |