Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 2051 | Bread, Cake, And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0835 # 02 Y:2022 | 02 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,773 | $7,150 | Implemented |
MA0835 # 04 Y:2022 | 04 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $680 | $750 | Implemented |
MA0835 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,572 | $40,722 | Implemented |
MA0836 # 03 Y:2022 | 03 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $9,895 | $23,950 | Implemented |
MA0836 # 05 Y:2022 | 05 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,531 | $1,500 | Implemented |
MA0836 # 06 Y:2022 | 06 | 2022 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $7,372 | $500 | Implemented |
MA0836 # 07 Y:2022 | 07 | 2022 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,777 | $7,150 | Implemented |
MA0836 # 08 Y:2022 | 08 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,781 | $625 | Implemented |
ME0185 # 09 Y:1996 | 09 | 1996 | CLOSE OFF UNNEEDED STEAM LINES | $812 | $1,850 | Implemented |
ME0185 # 08 Y:1996 | 08 | 1996 | INSULATE BARE EQUIPMENT | $660 | $1,000 | Implemented |
ME0185 # 07 Y:1996 | 07 | 1996 | INSULATE BARE EQUIPMENT | $655 | $1,000 | Implemented |
ME0185 # 06 Y:1996 | 06 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,128 | $70 | Implemented |
ME0185 # 05 Y:1996 | 05 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,854 | $1,050 | Implemented |
ME0185 # 04 Y:1996 | 04 | 1996 | OPTIMIZE PLANT POWER FACTOR | $4,144 | $5,290 | Implemented |
ME0185 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,255 | $1,200 | Implemented |
ME0185 # 02 Y:1996 | 02 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,498 | $5,100 | Implemented |
ME0185 # 01 Y:1996 | 01 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,254 | $2,600 | Implemented |
ME0141 # 08 Y:1994 | 08 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $164 | $70 | Implemented |
ME0141 # 05 Y:1994 | 05 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $619 | $400 | Implemented |
ME0141 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,292 | $0 | Implemented |
ME0141 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,764 | $2,080 | Implemented |