Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 2051 | Bread, Cake, And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0716 # 09 Y:2013 | 09 | 2013 | INSTALL OCCUPANCY SENSORS | $322 | $400 | Implemented |
MA0716 # 01 Y:2013 | 01 | 2013 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $33,408 | $70,705 | Implemented |
MA0716 # 02 Y:2013 | 02 | 2013 | ADOPT IN-HOUSE MATERIAL GENERATION | $20,977 | $22,000 | Implemented |
MA0716 # 03 Y:2013 | 03 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $18,072 | $35,000 | Implemented |
MA0716 # 04 Y:2013 | 04 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,554 | $10,000 | Implemented |
MA0716 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,726 | $10,000 | Implemented |
MA0716 # 06 Y:2013 | 06 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,965 | $6,300 | Implemented |
MA0716 # 07 Y:2013 | 07 | 2013 | INSULATE BARE EQUIPMENT | $1,343 | $935 | Implemented |
MA0716 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,141 | $4,000 | Implemented |
OR0613 # 07 Y:2013 | 07 | 2013 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $706 | $448 | Implemented |
OR0613 # 06 Y:2013 | 06 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $991 | $95 | Implemented |
OR0613 # 05 Y:2013 | 05 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,364 | $17,632 | Not Implemented |
OR0613 # 04 Y:2013 | 04 | 2013 | RECOVER AND REUSE WASTE MATERIAL | $3,635 | $8,000 | Not Implemented |
OR0613 # 03 Y:2013 | 03 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,262 | $36,000 | Implemented |
OR0613 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $3,040 | $2,913 | Not Implemented |
OR0613 # 01 Y:2013 | 01 | 2013 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $11,140 | $5,000 | Implemented |
AM0634 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $297 | $1,520 | Implemented |
AM0634 # 07 Y:2013 | 07 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $510 | $0 | Implemented |
AM0634 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $1,150 | $625 | Not Implemented |
AM0634 # 05 Y:2013 | 05 | 2013 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,600 | $0 | Not Implemented |
AM0634 # 04 Y:2013 | 04 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,350 | $1,100 | Not Implemented |
AM0634 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,780 | $60 | Implemented |
AM0634 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,620 | $1,000 | Implemented |
AM0634 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,630 | $12,080 | Implemented |