Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

998

matching recommendations
Reset
SIC 206 Sugar And Confectionery Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TA0057 # 05 Y:2003 05 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,300 $72 Implemented
TA0057 # 06 Y:2003 06 2003 INSTALL / REPAIR INSULATION ON STEAM LINES $550 $175 Not Implemented
TA0057 # 07 Y:2003 07 2003 INSULATE BARE EQUIPMENT $460 $336 Not Implemented
TA0057 # 08 Y:2003 08 2003 INSTALL OCCUPANCY SENSORS $275 $180 Implemented
TA0057 # 09 Y:2003 09 2003 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $240 $110 Not Implemented
TA0057 # 10 Y:2003 10 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $200 $395 Implemented
TA0057 # 11 Y:2003 11 2003 TURN OFF EQUIPMENT WHEN NOT IN USE $120 $0 Implemented
IA0315 # 01 Y:2003 01 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,493 $910 Implemented
IA0315 # 02 Y:2003 02 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,181 $1,942 Not Implemented
IA0315 # 03 Y:2003 03 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,631 $17,891 Implemented
IA0315 # 04 Y:2003 04 2003 INSTALL OCCUPANCY SENSORS $2,897 $6,565 Not Implemented
IA0315 # 05 Y:2003 05 2003 INSTALL OCCUPANCY SENSORS $1,093 $3,059 Not Implemented
IA0315 # 06 Y:2003 06 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $730 $514 Implemented
IA0315 # 07 Y:2003 07 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $755 $333 Not Implemented
IA0315 # 08 Y:2003 08 2003 DIRECT WARMEST AIR TO COMBUSTION INTAKE $5,584 $600 Implemented
LE0151 # 01 Y:2003 01 2003 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $3,947 $3,000 Implemented
LE0151 # 02 Y:2003 02 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $13,069 $0 Not Implemented
LE0151 # 03 Y:2003 03 2003 USE OPTIMUM THICKNESS INSULATION $51,426 $6,735 Implemented
LE0151 # 04 Y:2003 04 2003 USE SYNTHETIC LUBRICANT $7,733 $1,000 Not Implemented
LE0151 # 05 Y:2003 05 2003 INSTALL OCCUPANCY SENSORS $1,064 $4,425 Implemented
LE0151 # 06 Y:2003 06 2003 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,947 $0 Not Implemented
LE0151 # 07 Y:2003 07 2003 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $4,270 $0 Not Implemented
LE0151 # 08 Y:2003 08 2003 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,121 $1,000 Implemented
UU0032 # 01 Y:2002 01 2002 MOVE BOILER TO MORE EFFICIENT LOCATION $83 $86 Not Implemented
UU0032 # 02 Y:2002 02 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $4,155 $12,000 Not Implemented