Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,356
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0575 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $242,187 | $285,000 | n/a |
LE0575 # 07 Y:2024 | 07 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $83,526 | $121,547 | n/a |
LE0575 # 08 Y:2024 | 08 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,618 | $2,720 | n/a |
LE0575 # 09 Y:2024 | 09 | 2024 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $36,513 | $150,000 | n/a |
LE0575 # 10 Y:2024 | 10 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $25,217 | $144,000 | n/a |
TT0318 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $519,539 | $7,626,292 | n/a |
TT0318 # 02 Y:2024 | 02 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $25,497 | $30,000 | n/a |
TT0318 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $17,101 | $94 | n/a |
TT0318 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,027 | $65,640 | n/a |
TT0318 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,815 | $1,500 | n/a |
TT0318 # 06 Y:2024 | 06 | 2024 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $5,885 | $12,180 | n/a |
TT0318 # 07 Y:2024 | 07 | 2024 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $4,912 | $15,000 | n/a |
TT0318 # 08 Y:2024 | 08 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,783 | $460 | n/a |
UW2409 # 01 Y:2024 | 01 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $240,871 | $7,750 | Implemented |
UW2409 # 02 Y:2024 | 02 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $1,927 | $2,080 | Implemented |
UW2409 # 03 Y:2024 | 03 | 2024 | TREAT AND REUSE RINSE WATERS | $1,034,601 | $300,000 | Implemented |
UW2409 # 04 Y:2024 | 04 | 2024 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $16,446 | $18,600 | Implemented |
UW2409 # 05 Y:2024 | 05 | 2024 | REPLACE BOILER | $61,679 | $155,400 | Implemented |
UW2409 # 06 Y:2024 | 06 | 2024 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $72,261 | $271,830 | Implemented |
UW2409 # 07 Y:2024 | 07 | 2024 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $24,670 | $223,625 | Implemented |
IC0303 # 17 Y:2024 | 17 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,739 | $211 | Not Implemented |
IC0303 # 16 Y:2024 | 16 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $74,328 | $441,248 | Implemented |
IC0303 # 15 Y:2024 | 15 | 2024 | INSULATE BARE EQUIPMENT | $2,406 | $1,236 | Not Implemented |
IC0303 # 14 Y:2024 | 14 | 2024 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $774 | $36 | Not Implemented |
IC0303 # 13 Y:2024 | 13 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $3,324 | $1,624 | Implemented |