Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
48
matching recommendationsSIC | 2086 | Bottled And Canned Soft Drinks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0835 # 10 Y:2012 | 10 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,937 | $1,000 | Implemented |
OK0835 # 03 Y:2012 | 03 | 2012 | REPLACE BOILER | $10,532 | $96,000 | Not Implemented |
OK0835 # 02 Y:2012 | 02 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,644 | $17,103 | Not Implemented |
OK0835 # 01 Y:2012 | 01 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,445 | $1,500 | Implemented |
OK0835 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $538 | $3,183 | Implemented |
OK0835 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $815 | $5,126 | Not Implemented |
OK0835 # 06 Y:2012 | 06 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $18,902 | $19,520 | Not Implemented |
OK0835 # 07 Y:2012 | 07 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,139 | $33,990 | Not Implemented |
OK0835 # 08 Y:2012 | 08 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,097 | $24,155 | Not Implemented |
OK0835 # 09 Y:2012 | 09 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,068 | $1,288 | Not Implemented |
OK0835 # 11 Y:2012 | 11 | 2012 | PROVIDE PROPER MAINTENANCE OF MOTOR DRIVEN EQUIPMENT | $621 | $120 | Implemented |
OK0835 # 12 Y:2012 | 12 | 2012 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $31,425 | $0 | Implemented |
OK0835 # 13 Y:2012 | 13 | 2012 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $8,840 | $4,000 | Not Implemented |
OK0835 # 14 Y:2012 | 14 | 2012 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $987 | $240 | Not Implemented |
UM0411 # 05 Y:2012 | 05 | 2012 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $15,341 | $5,000 | Not Implemented |
UM0411 # 01 Y:2012 | 01 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,396 | $2,000 | Not Implemented |
UM0411 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,402 | $200 | Not Implemented |
UM0411 # 03 Y:2012 | 03 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $821 | $100 | Implemented |
UM0411 # 04 Y:2012 | 04 | 2012 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $56,000 | $225,000 | Not Implemented |
SF0420 # 13 Y:2012 | 13 | 2012 | MINIMIZE WATER USAGE | $677 | $0 | Not Implemented |
SF0420 # 12 Y:2012 | 12 | 2012 | MINIMIZE WATER USAGE | $5,598 | $0 | Not Implemented |
SF0420 # 11 Y:2012 | 11 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $147,442 | $498,340 | Not Implemented |
SF0420 # 10 Y:2012 | 10 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,461 | $9,543 | Not Implemented |
SF0420 # 09 Y:2012 | 09 | 2012 | BURN A LESS EXPENSIVE GRADE OF FUEL | $52,423 | $78,900 | Not Implemented |
SF0420 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $53,028 | $57,435 | Not Implemented |