Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
253
matching recommendationsSIC | 2087 | Flavoring Extracts And Syrups, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0301 # 08 Y:2002 | 08 | 2002 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $70,176 | $0 | Not Implemented |
UF0301 # 09 Y:2002 | 09 | 2002 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $56,304 | $376 | Not Implemented |
OR0410 # 01 Y:2002 | 01 | 2002 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $17,362 | $0 | Not Implemented |
OR0410 # 02 Y:2002 | 02 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,208 | $22,848 | Implemented |
OR0410 # 03 Y:2002 | 03 | 2002 | UPGRADE CONTROLS ON COMPRESSORS | $3,700 | $2,000 | Not Implemented |
OR0410 # 04 Y:2002 | 04 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,057 | $4,025 | Implemented |
OR0410 # 05 Y:2002 | 05 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $299 | $600 | Not Implemented |
LE0115 # 01 Y:2001 | 01 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $993 | $200 | Implemented |
LE0115 # 02 Y:2001 | 02 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,669 | $0 | Not Implemented |
LE0115 # 03 Y:2001 | 03 | 2001 | USE SYNTHETIC LUBRICANT | $2,381 | $400 | Not Implemented |
LE0115 # 04 Y:2001 | 04 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,572 | $0 | Implemented |
LE0115 # 05 Y:2001 | 05 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,057 | $1,225 | Implemented |
LE0115 # 06 Y:2001 | 06 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,260 | $15,500 | Not Implemented |
LE0115 # 07 Y:2001 | 07 | 2001 | INSULATE FEEDWATER TANK | $15,398 | $450 | Implemented |
LE0115 # 08 Y:2001 | 08 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,792 | $768 | Implemented |
OD0175 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,794 | $49,324 | Not Implemented |
OD0175 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $800 | $520 | Implemented |
UD0595 # 01 Y:2000 | 01 | 2000 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $330,000 | $0 | Not Implemented |
UD0595 # 02 Y:2000 | 02 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $96,096 | $106,000 | Not Implemented |
UD0595 # 03 Y:2000 | 03 | 2000 | CONDENSE OPERATION INTO ONE BUILDING | $14,451 | $5,000 | Not Implemented |
UD0595 # 04 Y:2000 | 04 | 2000 | REDUCE SCRAP PRODUCTION | $11,016 | $20,400 | Not Implemented |
UD0595 # 05 Y:2000 | 05 | 2000 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $8,851 | $2,000 | Not Implemented |
UD0595 # 06 Y:2000 | 06 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,230 | $846 | Not Implemented |
UF0223 # 01 Y:1999 | 01 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,463 | $0 | Not Implemented |
UF0223 # 02 Y:1999 | 02 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,615 | $50 | Implemented |