Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
150
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KS2324 # 04 Y:2023 | 04 | 2023 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $12,787 | $8,320 | n/a |
KS2324 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,738 | $5,480 | n/a |
KS2324 # 07 Y:2023 | 07 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $57,559 | $312,824 | n/a |
KS2324 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,860 | $598,739 | n/a |
KS2324 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $2,028 | $4,064 | n/a |
KS2324 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,344 | $22,467 | n/a |
KS2324 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $32,201 | $0 | n/a |
GT0960 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,810 | $1,850 | Implemented |
GT0960 # 04 Y:2021 | 04 | 2021 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $39,614 | $149,000 | Not Implemented |
GT0960 # 02 Y:2021 | 02 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,573 | $800 | Implemented |
GT0960 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,666 | $8,719 | Implemented |
GT0960 # 05 Y:2021 | 05 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $175,754 | $2,009,756 | Not Implemented |
UF0576 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,147 | $0 | Implemented |
UF0576 # 11 Y:2022 | 11 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $284,508 | $0 | Implemented |
UF0576 # 12 Y:2022 | 12 | 2022 | IMPROVE SPACE COMFORT CONDITIONING | $19,893 | $5,851 | Implemented |
UF0576 # 03 Y:2022 | 03 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29,479 | $16,283 | Implemented |
UF0576 # 07 Y:2022 | 07 | 2022 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $5,306 | $765 | Implemented |
UF0576 # 10 Y:2022 | 10 | 2022 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,400 | $1,449 | Implemented |
UF0576 # 02 Y:2022 | 02 | 2022 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $30,987 | $10,183 | Implemented |
UF0576 # 08 Y:2022 | 08 | 2022 | INSTALL TURBULATORS | $3,726 | $7,500 | Not Implemented |
UF0576 # 04 Y:2022 | 04 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $21,495 | $6,314 | Implemented |
UF0576 # 09 Y:2022 | 09 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,828 | $2,002 | Implemented |
UF0576 # 01 Y:2022 | 01 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $55,456 | $51,203 | Implemented |
UF0576 # 05 Y:2022 | 05 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $16,965 | $25,427 | Implemented |
GT0930 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,531 | $8,066 | Implemented |