Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

22

matching recommendations
Reset
SIC 209 Misc. Food And Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0877 # 01 Y:2013 01 2013 ELIMINATE THIRD SHIFT $75,782 $0 Implemented
UD0877 # 02 Y:2013 02 2013 METER WASTE WATER $18,660 $1,000 Implemented
UD0877 # 06 Y:2013 06 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,095 $0 Implemented
UD0877 # 08 Y:2013 08 2013 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $61,182 $25,000 Implemented
UD0877 # 09 Y:2013 09 2013 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $685 $2,000 Implemented
UD0592 # 04 Y:2000 04 2000 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $5,506 $2,000 Implemented
UD0592 # 02 Y:2000 02 2000 UPGRADE CONTROLS ON COMPRESSORS $8,655 $8,000 Implemented
UD0505 # 07 Y:1996 07 1996 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $1,640 $0 Implemented
UD0505 # 06 Y:1996 06 1996 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,448 $1,000 Implemented
UD0505 # 05 Y:1996 05 1996 RECOVER WASTE HEAT FROM EQUIPMENT $4,110 $6,000 Implemented
UD0505 # 04 Y:1996 04 1996 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $7,221 $500 Implemented
UD0505 # 03 Y:1996 03 1996 REPLACE WATER COOLING ON PROCESSES WITH AIR COOLING $8,648 $4,000 Implemented
UD0505 # 02 Y:1996 02 1996 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,214 $0 Implemented
UD0505 # 01 Y:1996 01 1996 OPTIMIZE PLANT POWER FACTOR $12,351 $9,000 Implemented
UD0284 # 06 Y:1989 06 1989 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,404 $2,300 Implemented
UD0284 # 05 Y:1989 05 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,648 $0 Implemented
UD0284 # 04 Y:1989 04 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,210 $0 Implemented
UD0284 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,285 $0 Implemented
UD0284 # 01 Y:1989 01 1989 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $38,356 $20,000 Implemented
UD0166 # 03 Y:1985 03 1985 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $19,258 $50,000 Implemented
UD0166 # 02 Y:1985 02 1985 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $28,600 $40,000 Implemented
UD0166 # 01 Y:1985 01 1985 RECOVER AND REUSE COOLING WATER $10,849 $7,160 Implemented