Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
238
matching recommendationsSIC | 2096 | Potato Chips And Similar Snacks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0162 # 06 Y:1996 | 06 | 1996 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $450 | $750 | Implemented |
IA0162 # 08 Y:1996 | 08 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $73 | $94 | Implemented |
AS0189 # 01 Y:1996 | 01 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,388 | $10,000 | Implemented |
AS0189 # 02 Y:1996 | 02 | 1996 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,466 | $4,200 | Implemented |
AS0189 # 03 Y:1996 | 03 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $932 | $2,080 | Implemented |
AS0189 # 10 Y:1996 | 10 | 1996 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $96 | $100 | Implemented |
ME0196 # 01 Y:1996 | 01 | 1996 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,928 | $0 | Implemented |
ME0196 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,035 | $9,015 | Implemented |
ME0196 # 04 Y:1996 | 04 | 1996 | PAY UTILITY BILLS ON TIME | $628 | $0 | Implemented |
ME0196 # 05 Y:1996 | 05 | 1996 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $626 | $1,075 | Implemented |
ME0196 # 06 Y:1996 | 06 | 1996 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $397 | $1,000 | Implemented |
ME0196 # 07 Y:1996 | 07 | 1996 | INSULATE BARE EQUIPMENT | $236 | $126 | Implemented |
ME0196 # 08 Y:1996 | 08 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $229 | $300 | Implemented |
ME0196 # 09 Y:1996 | 09 | 1996 | MINIMIZE WATER USAGE | $928 | $250 | Implemented |
KU0457 # 02 Y:1996 | 02 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,591 | $1,000 | Implemented |
KU0457 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,835 | $10,180 | Implemented |
KU0457 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,711 | $1,800 | Implemented |
KU0457 # 05 Y:1996 | 05 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,034 | $3,130 | Implemented |
KU0457 # 06 Y:1996 | 06 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $813 | $155 | Implemented |
KU0457 # 07 Y:1996 | 07 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $592 | $165 | Implemented |
KU0457 # 08 Y:1996 | 08 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $433 | $663 | Implemented |
KU0457 # 09 Y:1996 | 09 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $272 | $480 | Implemented |
UF0139 # 01 Y:1996 | 01 | 1996 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $75,430 | $0 | Implemented |
UF0139 # 02 Y:1996 | 02 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $18,648 | $0 | Implemented |
UF0139 # 05 Y:1996 | 05 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,506 | $350 | Implemented |