Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
153
matching recommendationsSIC | 2099 | Food Preparations, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0013 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,556 | $4,600 | Not Implemented |
SJ0013 # 09 Y:2024 | 09 | 2024 | COMBINE UTILITY METERS | $454 | $0 | Not Implemented |
SJ0013 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,814 | $107,262 | Not Implemented |
SJ0013 # 06 Y:2024 | 06 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $20,579 | $0 | Not Implemented |
SJ0013 # 08 Y:2024 | 08 | 2024 | INSULATE BARE EQUIPMENT | $1,399 | $1,473 | Not Implemented |
SJ0013 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,372 | $104 | Not Implemented |
SJ0013 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $733 | $0 | Not Implemented |
SJ0013 # 03 Y:2024 | 03 | 2024 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $28 | $235 | Not Implemented |
SJ0013 # 07 Y:2024 | 07 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $155 | $22 | Not Implemented |
CI0022 # 06 Y:2023 | 06 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $5,312 | $50 | n/a |
CI0022 # 08 Y:2023 | 08 | 2023 | INSTALL OCCUPANCY SENSORS | $1,670 | $1,125 | n/a |
CI0022 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,547 | $7,400 | n/a |
CI0022 # 05 Y:2023 | 05 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,784 | $0 | n/a |
CI0022 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,948 | $300 | n/a |
CI0022 # 03 Y:2023 | 03 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $17,839 | $9,000 | n/a |
CI0022 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $18,385 | $60,000 | n/a |
CI0022 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $30,795 | $185,422 | n/a |
CI0017 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $271,104 | $1,391,144 | n/a |
CI0017 # 08 Y:2023 | 08 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,591 | $5,000 | n/a |
CI0017 # 07 Y:2023 | 07 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,491 | $0 | n/a |
CI0017 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,433 | $1,500 | n/a |
CI0017 # 05 Y:2023 | 05 | 2023 | USE POWER DURING OFF-PEAK PERIODS | $12,483 | $22,000 | n/a |
CI0017 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,971 | $39,000 | n/a |
CI0017 # 03 Y:2023 | 03 | 2023 | REPLACE BOILER | $25,947 | $36,000 | n/a |
CI0017 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $63,711 | $90,000 | n/a |