Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
101
matching recommendationsSIC | 2099 | Food Preparations, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0439 # 03 Y:2003 | 03 | 2003 | REDUCE OR ELIMINATE WASTE | $36,600 | $220 | Implemented |
AM0439 # 04 Y:2003 | 04 | 2003 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $31,700 | $270 | Implemented |
AM0439 # 05 Y:2003 | 05 | 2003 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $15,600 | $500 | Implemented |
AM0439 # 06 Y:2003 | 06 | 2003 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $13,200 | $7,600 | Implemented |
AM0439 # 07 Y:2003 | 07 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,400 | $1,000 | Implemented |
AM0439 # 08 Y:2003 | 08 | 2003 | REPAIR OR REPLACE STEAM TRAPS | $7,600 | $1,120 | Implemented |
AM0439 # 09 Y:2003 | 09 | 2003 | INSULATE BARE EQUIPMENT | $4,890 | $550 | Implemented |
AM0439 # 10 Y:2003 | 10 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,500 | $980 | Implemented |
AM0439 # 11 Y:2003 | 11 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,290 | $1,460 | Implemented |
AM0439 # 12 Y:2003 | 12 | 2003 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,140 | $400 | Implemented |
TA0050 # 01 Y:2003 | 01 | 2003 | UPGRADE CONVEYORS | $430,950 | $202,900 | Not Implemented |
TA0050 # 02 Y:2003 | 02 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $47,100 | $5,202 | Implemented |
TA0050 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,258 | $8,100 | Implemented |
TA0050 # 04 Y:2003 | 04 | 2003 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $13,150 | $0 | Not Implemented |
TA0050 # 05 Y:2003 | 05 | 2003 | UPGRADE OBSOLETE EQUIPMENT | $5,795 | $11,200 | Implemented |
TA0050 # 06 Y:2003 | 06 | 2003 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $4,492 | $0 | Not Implemented |
TA0050 # 07 Y:2003 | 07 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,570 | $0 | Implemented |
TA0050 # 08 Y:2003 | 08 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,676 | $0 | Implemented |
TA0050 # 09 Y:2003 | 09 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $390 | $0 | Not Implemented |
TA0050 # 10 Y:2003 | 10 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $390 | $0 | Implemented |
KG0026 # 01 Y:1995 | 01 | 1995 | HEAT WATER WITH EXHAUST HEAT | $14,224 | $2,500 | Implemented |
KG0026 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,694 | $0 | Implemented |
KG0026 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,123 | $1,850 | Implemented |
KG0026 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,076 | $183 | Implemented |
KG0026 # 05 Y:1995 | 05 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $823 | $300 | Implemented |