Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,498
matching recommendationsSIC | 2099 | Food Preparations, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0554 # 07 Y:2023 | 07 | 2023 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $31,394 | $144,000 | Not Implemented |
LE0554 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $873 | $2,700 | Implemented |
LE0554 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,367 | $4,000 | Implemented |
LE0554 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,979 | $40,491 | Implemented |
LE0554 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,873 | $35,440 | Implemented |
LE0554 # 02 Y:2023 | 02 | 2023 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,747 | $5,000 | Implemented |
LE0554 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,649 | $26,194 | Implemented |
CI0017 # 08 Y:2023 | 08 | 2023 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,591 | $5,000 | n/a |
CI0017 # 07 Y:2023 | 07 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,491 | $0 | n/a |
CI0017 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,433 | $1,500 | n/a |
CI0017 # 05 Y:2023 | 05 | 2023 | USE POWER DURING OFF-PEAK PERIODS | $12,483 | $22,000 | n/a |
CI0017 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,971 | $39,000 | n/a |
CI0017 # 03 Y:2023 | 03 | 2023 | REPLACE BOILER | $25,947 | $36,000 | n/a |
CI0017 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $63,711 | $90,000 | n/a |
CI0017 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $271,104 | $1,391,144 | n/a |
UU0224 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,460 | $1,382 | Implemented |
UU0224 # 05 Y:2023 | 05 | 2023 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $2,224 | $4,500 | Not Implemented |
UU0224 # 04 Y:2023 | 04 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,361 | $1,485 | Implemented |
UU0224 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,006 | $10,650 | Implemented |
UU0224 # 02 Y:2023 | 02 | 2023 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $10,206 | $7,560 | Implemented |
UU0224 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,006 | $51 | Implemented |
TR0042 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $141 | $52 | Implemented |
TR0042 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,568 | $395,038 | Not Implemented |
TR0042 # 03 Y:2022 | 03 | 2022 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $18,544 | $6,243 | Implemented |
UL2303 # 07 Y:2023 | 07 | 2023 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $6,194 | $25,900 | Not Implemented |