Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,268
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0556 # 02 Y:2024 | 02 | 2024 | DISCONNECT BALLASTS | $1,105 | $0 | Implemented |
SU0556 # 09 Y:2024 | 09 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $998 | $553 | Implemented |
SU0556 # 10 Y:2024 | 10 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $18,784 | $12,106 | Implemented |
SU0556 # 11 Y:2024 | 11 | 2024 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $7,286 | $4,767 | Implemented |
SU0556 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,916 | $12,528 | Implemented |
SU0556 # 13 Y:2024 | 13 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $766 | $771 | Implemented |
SU0556 # 14 Y:2024 | 14 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $402 | $537 | Implemented |
SU0556 # 15 Y:2024 | 15 | 2024 | INSTALL OCCUPANCY SENSORS | $557 | $1,283 | Implemented |
SU0556 # 16 Y:2024 | 16 | 2024 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $9,480 | $25,942 | Not Implemented |
SU0556 # 17 Y:2024 | 17 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $240,268 | $897,305 | Not Implemented |
SU0556 # 01 Y:2024 | 01 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,634 | $0 | Implemented |
KS2431 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $52,635 | $494,620 | n/a |
KS2431 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $10,405 | $31,750 | n/a |
KS2431 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,895 | $154,122 | n/a |
KS2431 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,373 | $5,480 | n/a |
KS2431 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $37,021 | $362,701 | n/a |
UD1085 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,525 | $0 | Not Implemented |
UD1085 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,415 | $0 | Not Implemented |
UD1085 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,452 | $1,235 | Implemented |
UD1085 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $168 | $52 | Not Implemented |
UD1085 # 05 Y:2024 | 05 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,170 | $760 | Not Implemented |
UD1085 # 06 Y:2024 | 06 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $58,447 | $0 | Not Implemented |
UD1085 # 07 Y:2024 | 07 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,159 | $20,475 | Not Implemented |
UD1085 # 08 Y:2024 | 08 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,403 | $20,475 | Not Implemented |
UD1085 # 09 Y:2024 | 09 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,175 | $3,294 | Not Implemented |