Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,239
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0092 # 04 Y:1997 | 04 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $562 | $2,705 | Implemented |
OD0092 # 05 Y:1997 | 05 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,299 | $9,865 | Implemented |
OD0092 # 06 Y:1997 | 06 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $10,500 | $4,095 | Implemented |
OD0092 # 07 Y:1997 | 07 | 1997 | INSTALL SOLID WASTE INCINERATOR FOR HEAT | $44,642 | $16,696 | Not Implemented |
HO0161 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,362 | $11,311 | Implemented |
HO0161 # 02 Y:1997 | 02 | 1997 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,635 | $1,878 | Not Implemented |
HO0161 # 03 Y:1997 | 03 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $723 | $385 | Implemented |
HO0161 # 04 Y:1997 | 04 | 1997 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $4,370 | $5,000 | Not Implemented |
HO0161 # 05 Y:1997 | 05 | 1997 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $480 | $100 | Implemented |
HO0161 # 06 Y:1997 | 06 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,130 | $100 | Not Implemented |
HO0161 # 07 Y:1997 | 07 | 1997 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $12,500 | $2,000 | Implemented |
GT0622 # 01 Y:1997 | 01 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $980 | $2,000 | Implemented |
GT0622 # 02 Y:1997 | 02 | 1997 | REPAIR AND ELIMINATE STEAM LEAKS | $3,470 | $1,200 | Implemented |
GT0622 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $94 | $240 | Not Implemented |
GT0622 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,626 | $300 | Implemented |
GT0622 # 05 Y:1997 | 05 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,060 | $632 | Implemented |
GT0622 # 06 Y:1997 | 06 | 1997 | MINIMIZE WATER USAGE | $533 | $0 | Not Implemented |
GT0622 # 07 Y:1997 | 07 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,999 | $3,200 | Not Implemented |
GT0622 # 08 Y:1997 | 08 | 1997 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $207,108 | $330,000 | Not Implemented |
GT0622 # 09 Y:1997 | 09 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,890 | $0 | Not Implemented |
OD0086 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $740 | $1,659 | Not Implemented |
OD0086 # 02 Y:1997 | 02 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,489 | $2,400 | Implemented |
OD0086 # 03 Y:1997 | 03 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,515 | $1,500 | Implemented |
OD0086 # 04 Y:1997 | 04 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $900 | $0 | Not Implemented |
OD0086 # 05 Y:1997 | 05 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $594 | $0 | Not Implemented |