Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
386
matching recommendationsSIC | 221 | Broadwoven Fabric Mills, Cotton |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AT0069 # 03 Y:1987 | 03 | 1987 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $982 | $2,500 | Not Implemented |
AT0069 # 04 Y:1987 | 04 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $99 | $150 | Not Implemented |
GT0307 # 01 Y:1987 | 01 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $775 | $300 | Implemented |
GT0307 # 02 Y:1987 | 02 | 1987 | IMPROVE LUBRICATION PRACTICES | $17,890 | $0 | Implemented |
GT0307 # 03 Y:1987 | 03 | 1987 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $10,669 | $7,000 | Implemented |
GT0307 # 04 Y:1987 | 04 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $16,327 | $12,600 | Implemented |
GT0307 # 05 Y:1987 | 05 | 1987 | KEEP LAMPS AND REFLECTORS CLEAN | $57,046 | $102,000 | Not Implemented |
GT0307 # 06 Y:1987 | 06 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,381 | $600 | Implemented |
GT0307 # 07 Y:1987 | 07 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,314 | $2,805 | Not Implemented |
GT0307 # 08 Y:1987 | 08 | 1987 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,742 | $37,500 | Implemented |
GT0270 # 01 Y:1985 | 01 | 1985 | INSTALL / REPAIR INSULATION ON STEAM LINES | $16,256 | $9,655 | Implemented |
GT0270 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,036 | $10,000 | Implemented |
GT0270 # 03 Y:1985 | 03 | 1985 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $912 | $980 | Implemented |
GT0270 # 04 Y:1985 | 04 | 1985 | INSULATE BARE EQUIPMENT | $1,824 | $3,150 | Implemented |
GT0270 # 05 Y:1985 | 05 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $195 | $200 | Implemented |
GT0270 # 06 Y:1985 | 06 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,003 | $1,186 | Not Implemented |
GT0270 # 07 Y:1985 | 07 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $730 | $727 | Implemented |
GT0270 # 08 Y:1985 | 08 | 1985 | INSULATE BARE EQUIPMENT | $25,166 | $83,600 | Not Implemented |
GT0270 # 09 Y:1985 | 09 | 1985 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $5,015 | $22,000 | Not Implemented |
GT0243 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $594 | $158 | Implemented |
GT0243 # 02 Y:1985 | 02 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $499 | $2,000 | Not Implemented |
GT0243 # 03 Y:1985 | 03 | 1985 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $38 | $0 | Not Implemented |
GT0243 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $20 | $50 | Implemented |
GT0243 # 05 Y:1985 | 05 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $73 | $0 | Not Implemented |
GT0173 # 01 Y:1983 | 01 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,420 | $50 | Not Implemented |