IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

22

matching recommendations
Reset
SIC 2295 Coated Fabrics, Not Rubberized
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0116 # 02 Y:2013 02 2013 INSTALL TIMERS AND/OR THERMOSTATS $5,700 $20 Implemented
DL0116 # 13 Y:2013 13 2013 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $6,946 $5,250 Not Implemented
DL0116 # 12 Y:2013 12 2013 INSULATE BARE EQUIPMENT $596 $500 Implemented
DL0116 # 11 Y:2013 11 2013 VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE $1,741 $800 Not Implemented
DL0116 # 10 Y:2013 10 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,316 $8,800 Not Implemented
DL0116 # 09 Y:2013 09 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,087 $22,969 Not Implemented
DL0116 # 08 Y:2013 08 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,226 $12,000 Implemented
DL0116 # 07 Y:2013 07 2013 RECOVER WASTE HEAT FROM EQUIPMENT $25,430 $24,500 Not Implemented
DL0116 # 06 Y:2013 06 2013 REPAIR AND ELIMINATE STEAM LEAKS $3,323 $4,000 Implemented
DL0116 # 05 Y:2013 05 2013 REDUCE VENTILATION AIR $11,206 $100 Not Implemented
DL0116 # 04 Y:2013 04 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,766 $11,200 Not Implemented
DL0116 # 03 Y:2013 03 2013 REDUCE VENTILATION AIR $2,320 $100 Not Implemented
DL0116 # 01 Y:2013 01 2013 RECOVER WASTE HEAT FROM EQUIPMENT $16,300 $10,000 Not Implemented
RU0097 # 01 Y:1990 01 1990 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $631 $0 Implemented
RU0097 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,503 $291 Not Implemented
RU0097 # 03 Y:1990 03 1990 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,103 $302 Implemented
RU0097 # 04 Y:1990 04 1990 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $218 $171 Implemented
RU0097 # 05 Y:1990 05 1990 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,004 $0 Not Implemented
RU0097 # 06 Y:1990 06 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,450 $0 Implemented
RU0097 # 07 Y:1990 07 1990 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,951 $500 Implemented
RU0097 # 08 Y:1990 08 1990 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $38,171 $13,250 Not Implemented
RU0097 # 09 Y:1990 09 1990 INSULATE BARE EQUIPMENT $1,424 $625 Implemented