Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

355

matching recommendations
Reset
SIC 2299 Textile Goods, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CI0030 # 09 Y:2024 09 2024 RECOVER WASTE HEAT FROM EQUIPMENT $2,030 $5,000 n/a
CI0030 # 08 Y:2024 08 2024 REPAIR AND ELIMINATE STEAM LEAKS $2,431 $4,000 n/a
CI0030 # 07 Y:2024 07 2024 USE PHOTOCELL CONTROLS $3,830 $1,500 n/a
CI0030 # 06 Y:2024 06 2024 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,914 $1,600 n/a
CI0030 # 05 Y:2024 05 2024 INSULATE BARE EQUIPMENT $4,265 $2,565 n/a
CI0030 # 04 Y:2024 04 2024 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $4,601 $18,900 n/a
CI0030 # 01 Y:2024 01 2024 USE SOLAR HEAT TO MAKE ELECTRICTY $21,581 $101,332 n/a
CI0030 # 02 Y:2024 02 2024 REPAIR OR REPLACE STEAM TRAPS $15,868 $1,600 n/a
CI0030 # 03 Y:2024 03 2024 INSTALL OCCUPANCY SENSORS $8,384 $3,000 n/a
GT0962 # 05 Y:2023 05 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $14,615 $35,774 Not Implemented
GT0962 # 01 Y:2023 01 2023 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $5,691 $200 Not Implemented
GT0962 # 04 Y:2023 04 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,117 $13,039 Not Implemented
GT0962 # 06 Y:2023 06 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $169,075 $2,808,032 Not Implemented
GT0962 # 02 Y:2023 02 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $30,443 $1,850 Not Implemented
GT0962 # 03 Y:2023 03 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $9,943 $800 Not Implemented
KS2203 # 02 Y:2022 02 2022 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,131 $0 Implemented
KS2203 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,941 $13,595 Implemented
KS2203 # 08 Y:2022 08 2022 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $10,802 $59,793 Not Implemented
KS2203 # 06 Y:2022 06 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,676 $45 Implemented
KS2203 # 03 Y:2022 03 2022 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $27,117 $60,601 Not Implemented
KS2203 # 05 Y:2022 05 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,656 $5,480 Implemented
KS2203 # 04 Y:2022 04 2022 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $98,216 $570,000 Implemented
KS2203 # 01 Y:2022 01 2022 INSTALL / REPAIR INSULATION ON STEAM LINES $6,958 $5,101 Implemented
CL1802 # 04 Y:2018 04 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,272 $2,080 Not Implemented
CL1802 # 05 Y:2018 05 2018 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $1,710 $250 Not Implemented