Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,394
matching recommendationsSIC | 23 | Apparel And Other Textile Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0623 # 05 Y:2018 | 05 | 2018 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $14,884 | $10,000 | Not Implemented |
NC0623 # 04 Y:2018 | 04 | 2018 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,478 | $16,800 | Implemented |
NC0623 # 03 Y:2018 | 03 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,320 | $1,203 | Implemented |
NC0623 # 02 Y:2018 | 02 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,322 | $900 | Implemented |
NC0623 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,801 | $500 | Implemented |
LE0462 # 05 Y:2018 | 05 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,454 | $24,417 | Implemented |
LE0462 # 04 Y:2018 | 04 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,005 | $2,000 | Not Implemented |
LE0462 # 03 Y:2018 | 03 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $226 | $355 | Implemented |
LE0462 # 02 Y:2018 | 02 | 2018 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $15,808 | $20,000 | Not Implemented |
LE0462 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,915 | $1,000 | Implemented |
UK1712 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $66,864 | $7,493 | Not Implemented |
UK1712 # 02 Y:2017 | 02 | 2017 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $37,683 | $0 | Not Implemented |
UK1712 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,140 | $11,343 | Not Implemented |
UK1712 # 04 Y:2017 | 04 | 2017 | INSTALL OCCUPANCY SENSORS | $1,664 | $1,288 | Not Implemented |
UK1712 # 05 Y:2017 | 05 | 2017 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $15,253 | $0 | Not Implemented |
UK1712 # 06 Y:2017 | 06 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,154 | $926 | Not Implemented |
UK1712 # 07 Y:2017 | 07 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $25,486 | $0 | Not Implemented |
UK1712 # 08 Y:2017 | 08 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $10,498 | $0 | Not Implemented |
UK1712 # 09 Y:2017 | 09 | 2017 | METER WASTE WATER | $6,463 | $0 | Not Implemented |
UK1712 # 10 Y:2017 | 10 | 2017 | METER WASTE WATER | $2,076 | $253 | Not Implemented |
UK1712 # 11 Y:2017 | 11 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,508 | $0 | Not Implemented |
UK1712 # 12 Y:2017 | 12 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $905 | $1,053 | Not Implemented |
UK1712 # 13 Y:2017 | 13 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,790 | $3,458 | Not Implemented |
UK1711 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,857 | $78,811 | Not Implemented |
UK1711 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,405 | $0 | Not Implemented |